BLD-Final | 8/23/2002 | 8/23/2002 | 8/23/2002 | | DONE |
|
|
|
Final/ok for perm. occ.
|
BLD-Final | 8/21/2002 | 8/22/2002 | 8/22/2002 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 08/21/2002 at 17:41:26. Contact: ###-####. Need all signatures for Perm Occ. Temp ....OK. 8/22/2002 2:41:35 PM
|
FIRE-Final Inspection | 8/20/2002 | 8/21/2002 | 8/21/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life/safety, fire alarm and fire sprinkler finaled 8/22/2002 9:13:14 AM
|
FIRE-Alarm Testing | 8/9/2002 | 8/12/2002 | 8/12/2002 | A | FAIL |
Troy Cobbley
|
|
|
no approved plans on site 8/12/2002 10:55:01 AM
|
BLD-Footing | 7/26/2002 | 7/26/2002 | 7/26/2002 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 08:22:14. Contact: ###-#### 7/26/2002 12:26:15 PM
|
BLD-Framing/Rough-in | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/16/2002 at 15:47:39. Contact: ###-####.west side grid ceiling ok. 7/17/2002 11:31:00 AM
|
FIRE-Conference | 7/16/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Troy Cobbley
|
|
|
sprinkler pipe is OK to cover in breakroom, conference room, east/west corridor and in the large open office. The small offices within the large open office need the hangers corrected 7/17/2002 1:00:32 PM
|
BLD-Framing/Rough-in | 6/28/2002 | 7/1/2002 | 7/1/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/28/2002 at 17:33:33. Contact: ###-####. grid ok int walls west side ok 7/1/2002 3:12:16 PM
|
BLD-Framing/Rough-in | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/12/2002 at 13:31:03. Contact: ###-####.grid. 6/13/2002 1:05:11 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/11/2002 | 6/11/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/10/2002 at 15:46:40. Contact: ###-####.ceiling needs perimeters. 6/11/2002 4:45:17 PM
|
FIRE-Conference | 6/4/2002 | 6/6/2002 | 6/6/2002 | A | DONE |
Troy Cobbley
|
|
|
rough-in OK in the data room and is ok to cover. 6/6/2002 11:03:33 AM
|
BLD-Framing/Rough-in | 5/15/2002 | 5/16/2002 | 5/16/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/15/2002 at 16:33:05. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/12/2002 | 4/15/2002 | 4/15/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/12/2002 at 11:03:58. Contact: ###-####.. needs ceiling grid at the data area approved by architect and grid mnf co. 4/15/2002 12:12:10 PM
|
BLD-Conference | 4/4/2002 | 4/5/2002 | 4/5/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/04/2002 at 15:23:12. Contact: ###-####.. went over ceiling grid in server area, unistrut design, appears ok as per plans. 4/5/2002 1:13:11 PM
|
BLD-Framing/Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PART |
Tom Arcoraci
|
|
|
###-#### kent ok to cover east side full height walls 3/21/2002 9:02:37 AM
|
BLD-Framing/Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 11:42:37. Contact: ###-####.
|