BLD-Final | 1/31/2002 | 1/31/2002 | 1/31/2002 | P | PASS |
Dave Hannah
|
|
|
###-#### JIM (FOR OCCUPANCY) ok for perm occ 1/31/2002 1:55:17 PM
|
Permanent Occupancy | | 1/31/2002 | 1/31/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/30/2002 | 1/30/2002 | 1/30/2002 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/30/2002 9:51:44 AM Fire alarm, fire sprinkler and fire life/safety finaled
|
BLD-Final | 12/5/2001 | 12/7/2001 | 12/7/2001 | A | PART |
Jim Sly
|
|
|
temp only jim ###-#### OK for Temp Occ....C/N... Need letter of appr from Eng for steel supporting folding door, Wrap (insulate) drains at sinks, Obtain Perm Occ status within 90 days of this notice. 12/7/2001 12:37:16 PM
|
FIRE-Final Inspection | 12/7/2001 | 12/7/2001 | 12/7/2001 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 12/7/2001 10:38:41 AM Fire life/safety finaled. Fire sprinkler finaled. Fire alarm given temp.
|
FIRE-Final Inspection | 12/6/2001 | 12/6/2001 | 12/6/2001 | P | NR |
Troy Cobbley
|
|
|
Met with contractor, went over obvious problems with return 12/7/01 12/6/2001 3:00:44 PM
|
BLD-Framing/Rough-in | 12/4/2001 | 12/4/2001 | 12/4/2001 | P | PART |
Jim Sly
|
|
|
###-#### jim East wall break room OK. 12/4/2001 1:22:54 PM
|
BLD-Framing/Rough-in | 11/29/2001 | 11/30/2001 | 11/30/2001 | A | PART |
Jim Sly
|
|
|
JIM ###-#### CELING GRID Ceiling OK 3 sm. Rms (West) 11/30/2001 10:30:15 AM
|
BLD-Footing | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | FAIL |
Jim Sly
|
|
|
ft insp jim ###-#### C/N Eng to approve....poured W/O insp. 11/9/2001 4:12:03 PM
|
BLD-Framing/Rough-in | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | PASS |
Jim Sly
|
|
|
jim--###-#### C/N for special insp of steel beam welding and Eng to approve footing poured W/O insp. 11/9/2001 4:13:26 PM
|