BLD-Final | 10/24/2002 | 10/25/2002 | 10/25/2002 | A | NH |
Jim Sly
|
|
|
###-#### No one on site.....No paperwork....called contact #.....No response. 10/25/2002 12:21:32 PM
|
BLD-Final | 10/25/2002 | 10/25/2002 | 10/25/2002 | P | PASS |
Jim Sly
|
|
|
OK for Perm. Occ. :)
|
Permanent Occupancy | | 10/25/2002 | 10/25/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/22/2002 | 10/23/2002 | 10/23/2002 | P | PASS |
Troy Cobbley
|
|
|
fire doors operated properly and sprinkler heads are OK. The contractor will install the sprinkler head canopies when the painter is finished 10/24/2002 9:04:32 AM
|
BLD-Other | 10/18/2002 | 10/21/2002 | 10/21/2002 | A | FAIL |
Russ Owen
|
|
|
nAIL INSPECT ###-#### RICK . posted c/n. 10/21/2002 3:07:49 PM
|
BLD-Framing/Rough-in | 10/16/2002 | 10/17/2002 | 10/17/2002 | P | PART |
Dave Hannah
|
|
|
###-#### walls are up but still needs to finish cieling rafters all steel studs also needs to finish above roll down doors contractor will call russ tomorrow I told him he could cover one side with sheet rock 10/17/2002 4:50:44 PM
|
BLD-Conference | 10/9/2002 | 10/9/2002 | 10/9/2002 | P | PART |
Russ Owen
|
|
|
meet with contractor about truck roll down doors. 10/9/2002 3:00:37 PM
|
BLD-Final | 9/18/2002 | 9/19/2002 | 9/19/2002 | A | NR |
Russ Owen
|
|
|
Curt, ###-####, and then 8, 2020 - let me know if you approve this - Cathy. This is not ready the work has not been done, there is a new plan to resolve the fire door issue at loading dock. 9/18/2002 4:16:59 PM
|
BLD-Conference | 8/13/2002 | 8/13/2002 | 8/13/2002 | P | PART |
Russ Owen
|
|
|
meet with plan checker and tennant to resolve c/n for roll up doors 1hr. 8/13/2002 4:40:54 PM
|
BLD-Conference | 6/25/2002 | 6/25/2002 | 6/25/2002 | A | CANC |
Russ Owen
|
|
|
|
BLD-Final | 6/10/2002 | 6/11/2002 | 6/11/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/10/2002 at 16:03:28. Contact: ###-####.Ok temp oc, c/n same for doors. 6/11/2002 12:44:32 PM
|
BLD-Final | 6/7/2002 | 6/7/2002 | 6/7/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/07/2002 at 06:55:29. Contact: .Loading dock roll down doors needs to be 1 hr rated, the door to stereo shop needs to be a 1 hr rated door, need special inspection final letter of completion. No c/n posted contractor on site notified. 6/7/2002 1:17:32 PM
|
BLD-Final | 6/5/2002 | 6/6/2002 | 6/6/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/05/2002 at 17:41:02. Contact: ###-####.. needs 4 hold downs only installed 2. Wrote this on existing c/n. 6/6/2002 4:15:29 PM 6/6/2002 4:15:49 PM
|
FIRE-Final Inspection | 6/6/2002 | 6/6/2002 | 6/6/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled
|
BLD-Final | 6/3/2002 | 6/5/2002 | 6/5/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/03/2002 at 10:04:52. Contact: ###-####. walk thru only ,needs all signatures on card will need to 6/5/2002 12:53:37 PM o recall. 6/5/2002 12:53:43 PM 6/5/2002 12:53:54 PM
|
FIRE-Alarm Testing | 6/3/2002 | 6/5/2002 | 6/5/2002 | A | NR |
Troy Cobbley
|
|
|
fire alarm contractor not ready 6/5/2002 8:20:24 AM
|
FIRE-Final Inspection | 6/3/2002 | 6/5/2002 | 6/5/2002 | A | NR |
Troy Cobbley
|
|
|
fire alarm contractor not ready 6/5/2002 8:20:48 AM
|
Code Occupancy Approval | | | 6/5/2002 | | PASS |
|
|
|
Meets compliance with DR - PASS
|
FIRE-Final Inspection | 5/13/2002 | 5/15/2002 | 5/15/2002 | A | FAIL |
Rick Jackson
|
|
|
fire fn- rick ###-#### not even close to being ready; tested front portion of emergency lights - several didn't work; some sprinklers have been painted or still have wrap on them - told GC to get TVFP out to check the heads again; extinguishers appear okay 5/15/2002 9:38:27 AM
|
BLD-Framing/Rough-in | 5/6/2002 | 5/7/2002 | 5/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/6/2002 7:01:15 PM . needs the bolts at the z bar 24 in oc. 5/7/2002 1:01:08 PM
|
BLD-Framing/Rough-in | 5/6/2002 | 5/6/2002 | 5/6/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/06/2002 at 07:38:19. Contact: ###-####.. need addnl bolts in z bar. also engineering stamped. 5/6/2002 7:01:52 PM
|
BLD-Framing/Rough-in | 5/2/2002 | 5/3/2002 | 5/3/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 5/2/2002 2:07:28 PM still waiting for eng detail for new conection at top of front of entry ok to start cover 5/3/2002 2:05:19 PM 5/3/2002 2:05:44 PM
|
BLD-Framing/Rough-in | 5/1/2002 | 5/2/2002 | 5/2/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 14:31:11. Contact: ###-####. Need approval from engineer for wall connections at front entry framing agains 5/2/2002 4:29:39 PM t cmu wall , no c/n as was not complete.5/2/2002 4:29:49 PM 5/2/2002 4:30:12 PM
|
BLD-Framing/Rough-in | 4/30/2002 | 5/1/2002 | 5/1/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/30/2002 at 10:58:06. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/15/2002 | 4/16/2002 | 4/16/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/15/2002 at 15:06:59. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/11/2002 | 4/12/2002 | 4/12/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/11/2002 at 19:04:46. Contact: ###-####.. ok need architect to suppy info for glue lam beam ie:1hr fire resistive. or drywall. notified framing contractor.4/12/2002 3:13:10 PM 4/12/2002 3:13:53 PM
|
BLD-Framing/Rough-in | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/02/2002 at 12:50:07. Contact: ###-####.sprinkler room. 4/3/2002 1:37:54 PM
|
BLD-Framing/Rough-in | 3/22/2002 | 3/25/2002 | 3/26/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/22/2002 2:06:36 PM
|
BLD-Framing/Rough-in | 3/22/2002 | 3/22/2002 | 3/22/2002 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/22/2002 at 07:06:30. Contact: ###-####. ' 3/22/2002 2:05:42 PM
|
BLD-Framing/Rough-in | 3/22/2002 | 3/22/2002 | 3/22/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/22/2002 2:01:39 PM . need a brace at the restroom. 3/22/2002 2:06:13 PM
|
BLD-Framing/Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 09:49:03. Contact: ###-####. need to add braces at both north and south areas ,went over these with contractor. 3/21/2002 4:33:12 PM
|
BLD-Foundation | 3/15/2002 | 3/18/2002 | 3/18/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 03/15/2002 at 17:34:47. Contact: ###-####. spec insp 3/18/2002 9:33:49 AM
|
BLD-Footing | 3/13/2002 | 3/14/2002 | 3/14/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/13/2002 at 10:15:21. Contact: ###-####. East end of new footing near completion . Also special inspection will be performed. 3/14/2002 11:00:13 AM p 3/14/2002 11:00:15 AM 3/14/2002 11:00:36 AM
|
BLD-Framing/Rough-in | 3/1/2002 | 3/4/2002 | 3/4/2002 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/01/2002 at 11:07:14. Contact: ###-####.c/n posted. 3/4/2002 3:30:21 PM
|
BLD-Framing/Rough-in | 3/4/2002 | 3/4/2002 | 3/4/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 3/4/2002 5:01:00 PM Rest room walls ok , a framed ceiling will be added after sheetrocking walls. 3/4/2002 5:25:25 PM
|
BLD-Concrete | 2/11/2002 | 2/11/2002 | 2/11/2002 | P | PART |
Russ Owen
|
|
|
###-#### partial trench inspection
|
BLD-Framing/Rough-in | 2/6/2002 | 2/7/2002 | 2/7/2002 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/06/2002 at 10:39:37. Contact: ###-####.wENT OVER PLANS AND PARTIAL INSPECTION OF TENN DIM WALL NEEDS ELE PRIOR TO COVER. 2/7/2002 12:11:16 PM
|