Permit Information
Permit NumberBLD01-02970
StatusFinaled
Name 300 MAIN - CORE WORK (VACANT)
Site Address 300 W MAIN ST
Project Name300 MAIN
Customer Number 
ePlanReviewNo
Description
(300 MAIN - CORE WORK) Remodel of an existing building with new building core work and dividing the building into vacant lease spaces for future office use tenants per approved plans on file. The building has a 12,028 sq. ft. first floor and will have a 6,368 sq. ft. second floor. The building also has a 1,280 sq. ft. basement for storage and mechanical/electrical equipment use. NO OCCUPANCY IS ALLOWED UNDER THIS PERMIT. Separate permits will be required for tenants to occupy any spaces. Work to include removing existing east stairway, constructing a new east stairway with handrails, new floor framing in former stair opening, new floor framing at west end of second floor, new exiting system design, providing new one-hour rated corridors/lobby & areas of refuge, new 20 minute rated doors where required, 45 minute wire glass in corridors where required, smoke/fire damper installations, new handrails/guardrails per code at existing stairways, one new exterior window installation in existing opening, new accessible core restrooms, interior finish, new suspended ceiling in some areas, some work in the basement, mechanical work, plumbing work, and electrical work. This is a Scope of Work Permit. LETTER OF COMPLETION TO BE ISSUED WHEN DONE. NOTE: This building is NOT fire sprinklered. (PC#0851-01) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/30/200312/30/200312/30/2003 PASS
DetailsDave Hannah
BLD-Final12/4/200212/4/200212/4/2002PPASS
DetailsCarl Dependahl
###-####, shell ok for l/c...split-level "storage" area to remain unfinished & deleted from shell permit. Further work in that area will require separate permits. Area is not for public access or storage use at this time and is to remain sealed/locked. 12/4/2002 2:59:57 PM
BLD-Final12/3/200212/4/200212/4/2002ANR
DetailsCarl Dependahl
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
FIRE-Final Inspection12/3/200212/4/200212/4/2002APASS
DetailsRick Jackson
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Final12/2/200212/3/200212/3/2002ANR
DetailsCarl Dependahl
dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...need fire ok, complete brg wall repairs (hinge point) at unfinished area 12/3/2002 10:23:35 AM
BLD-Final12/2/200212/3/200212/3/2002ACANC
DetailsCarl Dependahl
###-####
BLD-Conference11/26/200211/27/200211/27/2002APASS
DetailsCarl Dependahl
Dave ###-####, clarified c/n re "split-level " storage area, remove or cover foam insul...consult w/ fire re exit. 11/27/2002 10:36:03 AM
FIRE-Final Inspection11/26/200211/27/200211/27/2002ANR
DetailsRick Jackson
###-#### DAVE unoccupied space not ready 11/27/2002 11:34:27 AM
BLD-Final11/25/200211/26/200211/26/2002AFAIL
DetailsCarl Dependahl
DAVE THIS IS FOR OCCUPANCY; Phone #: ###-#### Internet Inspection Request from: Darla Downs, C/n: resolve exiting from "storage" area ...consult Rick Jackson; need eng'g or fix for studs at brg walls & all draftstopping installed at same ; cover or remove styrofoam exposed at wall. 11/26/2002 1:43:48 PM
BLD-Conference11/21/200211/21/200211/21/2002PPASS
DetailsCarl Dependahl
###-####...re final r'eq's, will resubmit to delete work at "unfinished"... 11/21/02 3:12:25 PM
BLD-Final11/20/200211/21/200211/21/2002ANR
DetailsCarl Dependahl
DAVE; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Conference11/19/200211/20/200211/20/2002APART
DetailsCarl Dependahl
dave ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie, keep c/n...need all insp reports...complete rails, etc. 11/20/02 3:16:47 PM
BLD-Framing/Rough-in11/6/200211/7/200211/7/2002APART
DetailsCarl Dependahl
fr & gen bld -dave; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie; wip at original shell (west stairs, 1hr lid in place ok to close walls pending other insps, keep c/n re final...need ext rails, etc., 11/7/2002 11:38:19 AM
BLD-Final10/30/200210/31/200210/31/2002PNR
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung...c/n, keep temp...need alll eng's/spec insp reports, complete guardrails at rear; verify p&z ok w/ site, etc... 10/31/02 5:11:49 PM
FIRE-Final Inspection10/31/200210/31/200210/31/2002APART
DetailsRick Jackson
disregard the fire final passed on this date; mistake entry by me; the center and east stair are complete per plans; still need to complete west stair and first floor northwest exit
FIRE-Final Inspection10/30/200210/31/200210/31/2002APASS
DetailsRick Jackson
dave ###-####
BLD-Other8/19/20028/20/20028/20/2002APASS
DetailsCarl Dependahl
DAVE ###-#### METAL FRAMING INSPECT...openings in concrete wall ok pending spec. insp/ eng's reports; eng'r to approve anchor bolt substitution. 8/20/2002 1:49:17 PM
BLD-Conference8/15/20028/16/20028/16/2002APASS
DetailsCarl Dependahl
###-#### DAVE met w/ bldr & Advanced Htg. (Gary)...ok to box out duct work over stairs if 1hr enclosure; exposed spiral duct at proposed 2nd fl.corridor ok if not serving corr. & sealed to SMACNA stds. 8/16/2002 11:14:24 AM
BLD-Conference8/12/20028/13/20028/13/2002APART
DetailsCarl Dependahl
dave; Phone #: ###-####; c/n, need eng's ok & spec. insp report for int cut concrete, resolve hand/guard rail issues for perm occ. 8/13/2002 10:49:35 AM
BLD-Conference8/8/20028/12/20028/12/2002ACANC
DetailsCarl Dependahl
DAVE ; Phone #: ###-####
FIRE-Final Inspection6/7/20026/10/20026/10/2002APART
DetailsRick Jackson
dave ###-#### met GC and went over requirements to sign this permit off 6/10/2002 2:03:01 PM
BLD-Conference5/31/20025/31/20025/31/2002PPASS
DetailsCarl Dependahl
w/ bldr re final req's: need eng's/ spec. insp reports...complete hand/guard rail installations...obtain all other perm finals.
BLD-Framing/Rough-in5/31/20025/31/20025/31/2002PPART
DetailsCarl Dependahl
###-#### DAVE elev. lobby ok to cover 5/31/2002 7:05:19 PM
BLD-Final5/9/20025/10/20025/10/2002AFAIL
DetailsCarl Dependahl
dave ###-#### see all c/ns, install rails, etc. 5/10/2002 12:41:22 PM
BLD-Framing/Rough-in5/9/20025/9/20025/9/2002APART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 05/09/2002 at 07:18:33. Contact: ###-####. Fir out walls on main and 2nd floor--ok to cover--north side only. 5/9/2002 10:22:10 AM
FIRE-Final Inspection5/9/20025/9/20025/9/2002APART
DetailsRick Jackson
Added by Inspector: 409 On 5/9/2002 8:15:51 AM temp only per Dave Miller; second floor not complete; NW exit not ready - not used for tenent under BLD02-00570; corridor complete on first floor
BLD-Final5/6/20025/6/20025/6/2002PFAIL
DetailsCarl Dependahl
FOR OCCUPANCY ###-#### DAVE
FIRE-Final Inspection5/6/20025/6/20025/6/2002PFAIL
DetailsRick Jackson
harold ###-#### fire fn exit signs; rated doors not installed; handrails not installed; address; detectors for AHU shutdown; elevator not complete/inspected nor alarm panel for recall; 5/6/2002 3:43:42 PM
BLD-Conference5/3/20025/3/20025/3/2002PPASS
DetailsCarl Dependahl
keep c/n, install rails or block stairs from use 5/3/2002 5:58:48 PM
BLD-Framing/Rough-in5/1/20025/2/20025/2/2002APART
DetailsCarl Dependahl
dave ###-#### ceiling insp grid ok at west end, ip on east a 5/2/2002 6:41:42 PM nd 1hr boxes at lids 5/2/2002 6:42:06 PM
BLD-Framing/Rough-in4/26/20024/29/20024/29/2002APART
DetailsCarl Dependahl
###-#### DAVE keep c/n, add boxes at recessed lights, firestop s as needed; ducts at corridor floor??? 4/29/2002 1:53:08 PM
BLD-Framing/Rough-in4/25/20024/25/20024/25/2002PFAIL
DetailsCarl Dependahl
dave ###-#### see c/n & previous c/n. 4/25/2002 6:53:04 PM
BLD-Conference4/2/20024/3/20024/3/2002AFAIL
DetailsCarl Dependahl
###-#### c/n need archs details for changes 4/3/2002 12:48:04 PM
BLD-Framing/Rough-in3/29/20023/29/20023/29/2002PFAIL
DetailsCarl Dependahl
fr ###-####