BLD-Final | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | PASS |
Jim Sly
|
|
|
###-#### DENNIS OK for Per Occ. 4/10/2002 12:47:30 PM
|
FIRE-Final Inspection | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety OK 4/10/2002 8:54:07 AM
|
Permanent Occupancy | | 4/10/2002 | 4/10/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PASS |
Troy Cobbley
|
|
|
fire life safety ok. Fire sprinklers failed 4/9/2002 11:32:50 AM
|
BLD-Wall cover | 3/26/2002 | 3/27/2002 | 3/27/2002 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/26/2002 at 15:01:04. Contact: ###-####. Server room 3/27/2002 4:23:27 PM
|
BLD-Final | 3/15/2002 | 3/18/2002 | 3/18/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/15/2002 at 16:18:19. Contact: ###-####. Phased constr. OK to Occupy Northwest offices......Fire Dept . checked for safety issues. 3/18/2002 9:54:49 AM
|
FIRE-Final Inspection | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | PART |
Troy Cobbley
|
|
|
Told contractor , Dennis, main exit is only one to be keyed all others to have approved hardware, to be verified at final. Fire extinguishers to be remounted at 48", provide approved fire sprinkler drawings. This inspection was for the northwest corner of tenant, other work needs to be completed. 3/15/2002 9:26:35 AM
|
BLD-Other | 3/13/2002 | 3/14/2002 | 3/14/2002 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/13/2002 at 16:20:05. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/28/2002 | 3/1/2002 | 3/1/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by Inspector: 407 On 2/28/2002 5:51:26 PM N. 1/2 f only 3/1/2002 3:00:55 PM
|
BLD-Framing/Rough-in | 2/27/2002 | 2/28/2002 | 2/28/2002 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/27/2002 at 15:33:21. Contact: ###-####. to many others this day recall for tomorow. 2/28/2002 5:53:16 PM
|