BLD-Final | 2/1/2002 | 2/4/2002 | 2/4/2002 | A | PASS |
Tony Young
|
|
|
steve ---fn-- ###-####
ok for perm. occ 2/4/2002 10:48:09 AMstripping will come on canopy permit 2/4/2002 10:49:10 AM
|
Permanent Occupancy | | 2/4/2002 | 2/4/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 2/1/2002 | 2/1/2002 | 2/1/2002 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/1/2002 10:17:43 AM Fire life/safety finaled
|
FIRE-Final Inspection | 1/30/2002 | 1/30/2002 | 1/30/2002 | A | FAIL |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/30/2002 10:00:41 AM provide current inspection tag for fire sprinkler riser, repair electric alarm bell on exterior of building, complete parking lot striping
|
BLD-Conference | 1/3/2002 | 1/4/2002 | 1/4/2002 | A | NR |
Tony Young
|
|
|
conference w/ Mike, 1/3/2002 4:08:00 PM
no plans yet via ph call 1/4/2002 11:34:28 AM
|
BLD-Conference | 1/4/2002 | 1/4/2002 | 1/4/2002 | P | PART |
Tony Young
|
|
|
conference on final 1/4/2002 11:32:57 AM
went over approved plans w/ mike z., issued a c/n and notice and order to vacate the building by jan. 31, 2002 for lack of cert. of occupancy. (it looks like they should be able to comply w/in this time as we are all working to achive this) 1/4/2002 4:02:47 PM
|
BLD-Conference | 1/2/2002 | 1/3/2002 | 1/3/2002 | A | CANC |
Tony Young
|
|
|
check plans, progress on c of o 1/2/2002 10:33:01 AM
|
BLD-Conference | 1/3/2002 | 1/3/2002 | 1/3/2002 | P | FAIL |
Tony Young
|
|
|
conference on getting c of o 1/3/2002 11:20:31 need approved plans, etc. 1/3/2002 4:09:00 PM
|
BLD-Conference | 12/31/2001 | 1/2/2002 | 1/2/2002 | A | FAIL |
Tony Young
|
|
|
Conference as requested. 325.
t/w Allan Koppel about plans, lack of occupancy, etc., he gave me name of Mike Zehner who is in charge of project, ###-#### or ###-####, I called mike, he said he will make some phone calls and get this taken care of, I scheduled my self out there next day to see plans and check on project 1/2/2002 11:02:12 AM
|
BLD-Conference | 12/18/2001 | 12/19/2001 | 12/19/2001 | P | DONE |
Troy Cobbley
|
|
|
Went over fire life/safety requirements for the project. Owner needs to change out door hardware 12/19/2001 3:58:00 PM
|
BLD-Conference | 12/18/2001 | 12/19/2001 | 12/19/2001 | A | NR |
Tony Young
|
|
|
MIKE ###-####
wants a fire inspector 12/19/2001 9:58:23 AM
|
BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | CANC |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 12/17/2001 10:21:57 AM
|
BLD-Conference | 12/17/2001 | 12/17/2001 | 12/17/2001 | P | DONE |
Tony Young
|
|
|
open w/out c of o ??? 12/17/2001 11:39:54 AM
occupancy violation,5 day notice issued
t/w Allan Koppel, he signed and received notice, said architect had the approved plans. 12/17/2001 3:21:37 PM
|