BLD-Final | 2/19/2003 | 2/20/2003 | 2/20/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/19/2003 at 12:09:34 PM. Contact: ###-####. c.c # 23790 issued 2/20/2003 12:32:41 PM
|
BLD-Final | 2/20/2003 | 2/20/2003 | 2/20/2003 | P | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 7/16/2002 | 7/16/2002 | 7/16/2002 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/16/2002 at 11:18:46. Contact: ###-####. c/n on site 7/16/2002 2:36:34 PM
|
BLD-Energy code compliance | 2/26/2002 | 2/27/2002 | 2/27/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/26/2002 at 18:34:23. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/22/2002 | 2/22/2002 | 2/22/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/22/2002 at 10:06:35. Contact: ###-####. ok to insulate 2/22/2002 2:19:40 PM
|
BLD-Other | 2/20/2002 | 2/20/2002 | 2/20/2002 | A | PASS |
Tony Young
|
|
|
Fire sprinklers not required per Dave Miller letter dated 2/11/02. 325.
|
BLD-Framing/Rough-in | 1/7/2002 | 1/8/2002 | 1/8/2002 | A | PART |
Jim Storey
|
|
|
###-#### rebar in place wip. 1/8/2002 10:45:45 AM
|
BLD-Footing | 1/4/2002 | 1/4/2002 | 1/4/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 01/04/2002 at 07:16:27. Contact: .
wip, some frost in ftg, 1-2", contacted Dale Berman, said he would call soil eng. and take full responsibility if they pour. 1/4/2002 11:50:04 AM
|
BLD-Grading Inspection | 1/4/2002 | 1/4/2002 | 1/4/2002 | | PASS |
Rita DeYoung
|
|
|
foundation subgrade has been approved by the geotechnical engineer.
|