Permit Information
Permit NumberBLD01-03251
StatusFinaled
Name RICHARD FRITZLEY
Site Address 3807 N HAWTHORNE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 2870 sq. ft. two story single family dwelling with a 1728 sq. ft. unfinished basement, a 620 sq. ft. covered concrete entry porch and a 96 sq. ft. concrete patio at rear of stucture per approved plans, all engineering/red-lining and attached requirement lists. (1st floor 1744 sq. ft.)(2nd floor 1126 sq. ft.) Note: See comments in condition list for additional information. Note: Seperate permits will be required to finish basement. PC #847 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/22/20034/23/20034/23/2003PPASS
DetailsTony Young
1. Plumbing is supposed to be inspected and passed in AM.
2. Permit to finish basement is BLD03-00873. I left copy on kitchen island counter for you.
3. House numbers are up.
I'm out of town on business. Call my cell phone if I need to answer any questions. Thanks.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
BLD-Final4/21/20034/22/20034/22/2003AFAIL
DetailsTony Young
Tony,
Exit door landings, steps, grading and sealing of exterior penetrations is complete. Ready for final. I have a meeting that begins at 10:00 AM, so if we could do this first thing, I would appreciate it. If not, go ahead without me. I'll leave the front door unlocked for you.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
c/n posted, need plumbing final, additional permit to finish basement,, note; all trades looked at basement at rough and final, perm. house #s, all else ok. 4/22/2003 9:33:13 AM
BLD-Conference4/14/20034/14/20034/14/2003APART
DetailsTony Young
Ready for final inspection pending final on subs. Want to do a walk through to know if I need to do anything else. Please call first so I can meet you there. Thanks; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
walk through w/ owner on final 4/14/2003 9:38:04 AM
BLD-Wall cover12/18/200212/18/200212/18/2002ACANC
DetailsTony Young
Tony,
Will only need this if the mechanical gets passed in the morning.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley Inspection cancelled from web by: Richard Fritzley
BLD-Energy code compliance12/18/200212/18/200212/18/2002PCANC
DetailsTony Young
Tony,
Sent seperate e-mail explaining what I had done to correct yesterday's deficiencies. I am out of town today so will not be able to be there for the inspection.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley Inspection cancelled from web by: Richard Fritzley
BLD-Energy code compliance12/18/200212/18/200212/18/2002APASS
DetailsTony Young
Tony,
I've corrected the deficiencies noted on yesterday's inspection. I scheduled the Wall Cover inspection for the afternoon to allow time to see if I passed Mechanical. Didn't know if you would be doing that again or if Dixie would be doing it. May want to coordinate to save a few trips. I will be out of town so no need to call me to let me know when you will be there. Thanks.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
BLD-Wall cover12/18/200212/18/200212/18/2002PPASS
DetailsTony Young
Tony,
No need to do this one if I don't pass the mechanical. I'll be out of town so no need to call me for the inspection. Thanks.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
ok to cover pending mech. pass 12/18/2002 1:03:47 PM
BLD-Energy code compliance12/16/200212/17/200212/17/2002APART
DetailsTony Young
Will also be scheduling Framing/Rough-in if you want to do both at the same time.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
need to seal more 12/17/2002 10:26:09 PM 12/17/2002 10:26:52 PM
BLD-Wall cover12/16/200212/17/200212/17/2002PFAIL
DetailsTony Young
HVAC subcontractor (Glynn's Heating & AC) is supposed to schedule their inspection for the morning, so this should be ready for you in the afternoon. I also scheduled the Energy code inspection for the morning, but you may want to do them both at the same time. Please call so I can get to the job site. It takes about 15 minutes to get there from my work. Thanks.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
c/n posted, ok to insulate 12/17/2002 10:28:28 PM
BLD-Framing/Rough-in12/12/200212/13/200212/13/2002PPART
DetailsTony Young
###-####
need trades 1st 12/13/2002 4:01:00 PM
BLD-Framing/Rough-in11/7/200211/8/200211/8/2002APART
DetailsTony Young
Please call first so I can be on site. Need about 20 minutes notice. Not quite ready for everything, but I received a notice that says my permit will expire in 10 days if I don't have an inspection. At least would like to get approval to start on siding. Can go over some other items too.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley,,, ext shear ok 11/8/2002 10:53:32 AM
BLD-Foundation5/2/20025/2/20025/2/2002PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/02/2002 at 07:14:46. Contact: ###-####.
BLD-Footing4/4/20024/5/20024/5/2002APART
DetailsTony Young
BLD-Footing4/1/20024/2/20024/2/2002APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 04/01/2002 at 12:14:38. Contact: ###-####. ftg / drain assy ok; setbacks ok per plan; proposed ice block type fdn/bsmt...told owner to recall when ready to pour. 4/2/2002 2:43:50 PM