BLD-Final | 5/13/2002 | 5/13/2002 | 5/13/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 05/13/2002 at 10:37:50. Contact: ###-####. c.c #23093 issued 5/13/2002 1:10:49 PM
|
BLD-Energy code compliance | 3/29/2002 | 4/1/2002 | 4/1/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/29/2002 at 18:19:52. Contact: ###-####.
|
BLD-Energy code compliance | 3/28/2002 | 3/29/2002 | 3/29/2002 | P | FAIL |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/28/2002 at 16:04:16. Contact: ###-####. c/n posted--Contractor to completed insulation and vapor barrier--call for re-inspection. 3/29/2002 1:29:53 PM
|
BLD-Framing/Rough-in | 3/27/2002 | 3/28/2002 | 3/28/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/27/2002 at 12:29:16. Contact: ###-####. ok to insulate 3/28/2002 3:49:48 PM
|
BLD-Other | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 12:01:50. Contact: ###-####. SHEAR--ok to side 3/21/2002 11:03:32 AM
|
BLD-Foundation | 2/4/2002 | 2/4/2002 | 2/4/2002 | P | PART |
Steven Webb
|
|
|
CLINT ###-#### WALL FOUNDATION wip--40% ready at time of inspection. 2/4/2002 2:14:54 PM
|
BLD-Footing | 1/31/2002 | 1/31/2002 | 1/31/2002 | P | PART |
Steven Webb
|
|
|
###-#### CLINT wip--5% ready at time of inspection 1/31/2002 1:39:45 PM
|