Permanent Occupancy | | 5/8/2002 | 5/8/2002 | | DONE |
|
|
|
|
BLD-Final | 4/14/2002 | 4/15/2002 | 4/15/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/14/2002 at 17:26:00. Contact: ###-####.final ok pending others sign off. 4/15/2002 11:12:38 AM
|
BLD-Final | 4/11/2002 | 4/12/2002 | 4/12/2002 | A | NR |
Jim Storey
|
|
|
TEMP OCC ###-####
|
BLD-Final | 4/9/2002 | 4/10/2002 | 4/10/2002 | P | NR |
Jim Storey
|
|
|
richard ###-#### temp occ
|
FIRE-Final Inspection | 4/9/2002 | 4/10/2002 | 4/10/2002 | P | PASS |
Rick Jackson
|
|
|
###-#### RICHARD will have address up for structural inspector 4/10/2002 2:41:04 PM
|
BLD-Framing/Rough-in | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PART |
Jim Storey
|
|
|
RICHARD ###-#### need spreader bars for primtor will check at final./ need single function hardware. 3/21/2002 2:32:38 PM
|
BLD-Framing/Rough-in | 2/19/2002 | 2/20/2002 | 2/20/2002 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/19/2002 at 12:52:58. Contact: . Framing for (North side) TI OK....Advised to rock /tenent Dem wall to ceiling (S. side) at areas of different ceiling height to complete 1hr separation. 2/20/2002 9:24:54 AM
|