Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD02-00175
StatusFinaled
Name RONALD MC DONALD HOUSE
Site Address 101 E WARM SPRINGS AVE
Project NameRONALD MCDONALD HOUSE
Customer Number 
ePlanReviewNo
Description
Ronald McDonald House Addition * To add 3,600 sq.ft. two stories, 7 guest sleeping rooms with bathrooms and a kitchen to the existing facility. Work to include renovating the existing 13 guest bedroom and removal of existing living room on the south end for new addition. All construction per the approved plans, CABO/ANSI A117.2-1992 and the attached comment list. NOTE: This building is fully fire sprinklered for one-hour substitution. DRH01-00238 MJP PC#058-02
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/17/200212/18/200212/18/2002APASS
DetailsSteven Webb
###-#### Signature by Public Works needed prior to issuance of C. of O. 12/18/2002 10:44:01 AM
Permanent Occupancy 12/18/200212/18/2002 DONE
Details
BLD-Conference12/11/200212/12/200212/12/2002PPASS
DetailsCarl Dependahl
w/ supt. keep c/n, wip. 12/12/2002 1:10:06 PM
BLD-Conference12/11/200212/11/200212/11/2002PNR
DetailsCarl Dependahl
gary--call 1st before insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
FIRE-Final Inspection12/4/200212/4/200212/4/2002APART
DetailsRick Jackson
awaiting calcs for new mini horns installed in rooms
BLD-Final12/2/200212/3/200212/3/2002PPART
DetailsCarl Dependahl
###-####...c/n, damper, "s"door labels at corridors...ok for t/o... 12/3/2002 4:58:46 PM
Code Occupancy Approval12/2/200212/2/200212/2/2002PPASS
DetailsWm. Michael Meloy
Compliance met. 12/2/2002 4:39:00 PM
FIRE-Final Inspection12/2/200212/2/200212/2/2002PFAIL
DetailsRick Jackson
###-#### supervised ball valves needed for antifreeze system; temporal horns in rooms; record of completion 12/2/2002 4:47:48 PM
FIRE-Conference11/26/200211/26/200211/26/2002PPART
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Amy Lawson met with Rod and alarm contractor; will attempt to test on Monday afternoon; reviewed plans; reviewed requirements for final 11/26/2002 1:50:41 PM
BLD-Conference10/28/200210/29/200210/29/2002APASS
DetailsCarl Dependahl
need 1hr door at laundry 10/29/02 4:53:50 PM
BLD-Energy code compliance10/8/200210/9/200210/9/2002APASS
DetailsSteven Webb
###-#### Air seal package completed. 10/9/2002 11:26:45 AM
BLD-Framing/Rough-in10/7/200210/8/200210/8/2002APART
DetailsCarl Dependahl
###-####...ok to insulate only...keep c/n (needs alarm approval but F.D. is allowing work to continue) 10/8/02 11:03:20 AM
BLD-Framing/Rough-in10/4/200210/7/200210/7/2002ANR
DetailsCarl Dependahl
###-#### ...keep c/n....firestopping, draftstops, eng's ok for multi-ply beam, air seal, etc...recall 10/7/2002 11:51:18 AM
BLD-Framing/Rough-in10/4/200210/4/200210/4/2002PNR
DetailsCarl Dependahl
###-#### after 3:30 pm. complete alarm install 10/4/2002 3:03:24 PM
BLD-Framing/Rough-in9/9/20029/10/20029/10/2002PFAIL
DetailsCarl Dependahl
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung...c/n,courtesy partial insp, 9/10/2002 4:14:10 PM
BLD-Conference8/12/20028/13/20028/13/2002APASS
DetailsCarl Dependahl
###-#### w/ bldr, arch, & mech eng'r.... install hvac per plan...will consult GS & advise. ok to "wrap" panel for 1hr const at occ sep. or corridor. 8/13/2002 11:53:23 AM
BLD-Conference8/13/20028/13/20028/13/2002PPASS
DetailsCarl Dependahl
W/ GS install hvac per plan... 8/13/2002 4:54:09 PM
BLD-Conference8/9/20028/12/20028/12/2002ACANC
DetailsCarl Dependahl
###-####
BLD-Conference8/8/20028/8/20028/8/2002PPASS
DetailsCarl Dependahl
###-####...add fireblocks, draft stops. brg for 2nd fl joists (32'?) need hvac consult w/ eng'r re corridor penetrations 8/8/2002 5:27:25 PM
BLD-Conference8/7/20028/7/20028/7/2002PCANC
DetailsCarl Dependahl
BLD-Conference8/7/20028/7/20028/7/2002PPASS
DetailsCarl Dependahl
w/ Rod...resubmittal rec'd, ok'd w/ notes re: relocate laundry & janitor's mop closet....
BLD-Framing/Rough-in7/25/20027/25/20027/25/2002PPART
DetailsTom Arcoraci
ROD; Phone #: ###-#### roof nailing ok 7/25/2002 2:09:46 PM
BLD-Framing/Rough-in7/24/20027/24/20027/24/2002PPART
DetailsDave Hannah
###-#### rod shear c/n items coplete on ext shear walls ok to cover 7/24/2002 1:01:07 PM
BLD-Framing/Rough-in7/23/20027/23/20027/23/2002PPART
DetailsTom Arcoraci
south shear wall ok east and west require 3 inch oc nailing ok to change laundry and janitor areas need new plans for resubmital check roof sheeting size 7/23/2002 2:11:55 PM
BLD-Foundation6/20/20026/20/20026/20/2002PPART
DetailsCarl Dependahl
ROBERT ###-####, steel ok, arch to advise re hd's & panel dimensions 6/20/2002 1:31:32 PM
BLD-Footing6/18/20026/19/20026/19/2002APART
DetailsCarl Dependahl
###-#### Robert Baker...steel in place, ok to pour ftg! 6/19/2002 11:21:51 AM
BLD-Foundation6/18/20026/18/20026/18/2002PPART
DetailsCarl Dependahl
JUSTIN ###-####...has MTI for epoxy dowels, ftg ok. 6/18/2002 4:07:13 PM