BLD-Aging Inspection | 5/30/2003 | 5/30/2003 | 5/30/2003 | | PASS |
Carl Dependahl
|
|
|
spoke w/ Jason, supt...l aranged insp w/ plans...all work complete, looks ok 6/3/2003 3:18:22 PM
|
FIRE-Final Inspection | 8/7/2002 | 8/8/2002 | 8/8/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/07/2002 at 15:11:38. Contact: ###-####. rated door not labeled; will have for structural inspector 8/8/2002 9:37:57 AM
|
FIRE-Final Inspection | 7/22/2002 | 7/22/2002 | 7/22/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/22/2002 at 07:29:53. Contact: ###-####. rated door for corridor not tagged; needs smoke seal and closure; temp door installed until rated door arrives in two weeks 7/22/2002 10:05:05 AM
|
FIRE-Alarm Testing | 7/19/2002 | 7/19/2002 | 7/19/2002 | P | NR |
Rick Jackson
|
|
|
###-#### will reschedule 7/19/2002 4:54:14 PM
|