BLD-Final | 7/6/2002 | 7/8/2002 | 7/8/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/06/2002 at 10:57:16. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/16/2002 | 4/18/2002 | 4/18/2002 | P | DONE |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/16/2002 at 07:40:01. Contact: ###-####.already done by 316 on 4/17 4/18/2002 2:36:56 PM
|
BLD-Framing/Rough-in | 4/17/2002 | 4/17/2002 | 4/17/2002 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 04/17/2002 at 09:45:52. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/1/2002 | 4/1/2002 | 4/1/2002 | P | FAIL |
Carl Dependahl
|
|
|
fr insp mike- ###-#### c/n, fnd insul,access, nailing at panels, verify plbg/hvac permits for existing bath remodel 4/1/2002 5:18:16 PM
|
BLD-Footing | 3/6/2002 | 3/7/2002 | 3/7/2002 | A | PART |
Tony Young
|
|
|
ft mike ###-####
forms on site, not set up, will be monolithic, t/w concrete sub contractor, ok 3/7/2002 10:01:16 AM
|
BLD-Footing | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/06/2002 at 05:30:32. Contact: ###-####.cancel per mike
|