BLD-Final | 8/20/2002 | 8/21/2002 | 8/21/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/20/2002 at 14:37:45. Contact: ###-####.
ok for perm. c of o 8/21/2002 12:32:39 PM
|
BLD-Final | 8/21/2002 | 8/21/2002 | 8/21/2002 | P | PASS |
Tony Young
|
|
|
###-#### 8/21/2002 11:11:08 AM
|
Permanent Occupancy | | 8/21/2002 | 8/21/2002 | | DONE |
|
|
|
|
BLD-Final | 8/19/2002 | 8/19/2002 | 8/19/2002 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 06:25:09. Contact: ###-####. JOHN CALLED IN TO CANC NOT READY YET
|
FIRE-Final Inspection | 8/19/2002 | 8/19/2002 | 8/19/2002 | A | PASS |
Troy Cobbley
|
|
|
fire life/safety finaled 8/19/2002 3:38:17 PM
|
BLD-Final | 8/14/2002 | 8/14/2002 | 8/14/2002 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/14/2002 at 06:59:25. Contact: ###-####.still working on handrail and other items 8/14/2002 4:29:29 PM
|
BLD-Final | 8/9/2002 | 8/12/2002 | 8/12/2002 | A | NR |
Dave Hannah
|
|
|
|
BLD-Final | 8/8/2002 | 8/9/2002 | 8/9/2002 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 08/08/2002 at 19:22:45. Contact: ###-####. unable to respond by 5 pm 8/9/2002 5:06:28 PM
|
FIRE-Final Inspection | 8/8/2002 | 8/9/2002 | 8/9/2002 | A | PART |
Troy Cobbley
|
|
|
a temporary occupancy was given until the contractor has two ductt smoke detectors installed. everything else is ok 8/9/2002 11:08:31 AM
|
BLD-Conference | 8/6/2002 | 8/7/2002 | 8/7/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/06/2002 at 19:13:51. Contact: ###-####.
conf. on final,, in general 8/7/2002 10:26:16 AM
|
FIRE-Conference | 6/24/2002 | 6/24/2002 | 6/24/2002 | A | DONE |
Troy Cobbley
|
|
|
spoke with the contractor about fire lane painting, emergency lights and exit signs
|
BLD-Wall cover | 6/11/2002 | 6/12/2002 | 6/12/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/11/2002 at 20:37:06. Contact: ###-####. OK to cover all Main floor Except center core Pending HVAC insp. VPA connections OK, Int. hold downs and blocking OK, Verbal.... 18" toilet, Add 1/2" to landing. 6/12/2002 10:38:53 AM 6/12/2002 10:40:12 AM
|
BLD-Framing/Rough-in | 6/6/2002 | 6/6/2002 | 6/6/2002 | P | PART |
Tony Young
|
|
|
fr ###-#### john
upstairs ok for cover////verify sealing of draft stops later 6/7/2002 10:33:01 AM
|
BLD-Framing/Rough-in | 6/5/2002 | 6/5/2002 | 6/5/2002 | P | FAIL |
Tony Young
|
|
|
###-#### john
|
BLD-Framing/Rough-in | 6/4/2002 | 6/4/2002 | 6/4/2002 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/04/2002 at 06:21:48. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/4/2002 | 6/4/2002 | 6/4/2002 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/04/2002 at 06:21:48. Contact: ###-####. no mech rough in 6/4/2002 4:30:09 PM
|
BLD-Framing/Rough-in | 5/13/2002 | 5/14/2002 | 5/14/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/13/2002 at 21:14:10. Contact: ###-####.
ext shear ok, verify 3 alt hds on west 5/14/2002 11:31:02 AM
|
BLD-Framing/Rough-in | 5/10/2002 | 5/10/2002 | 5/10/2002 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/10/2002 at 06:36:19. Contact: ###-####.
hds and nailing not complete 5/10/2002 8:59:59 AM
|
BLD-Other | 4/26/2002 | 4/26/2002 | 4/26/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/26/2002 at 06:49:33. Contact: ###-####.
diamond under columns for non shrink grout ok to continue 4/26/2002 9:15:25 AM
|
BLD-Foundation | 4/12/2002 | 4/12/2002 | 4/12/2002 | P | PART |
Dave Hannah
|
|
|
###-#### int column pads also ext column foundations four of the ftgs are off by about 2ft arc neededs to appr fix ok to pour after he oks 4/12/2002 1:56:45 PM
|
BLD-Footing | 4/11/2002 | 4/11/2002 | 4/11/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/11/2002 at 05:49:28. Contact: ###-####. ext. isolated ftgs poured, look ok. 4/11/2002 5:47:00 PM
|
BLD-Foundation | 4/10/2002 | 4/11/2002 | 4/11/2002 | A | DONE |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/10/2002 at 12:47:33. Contact: ###-####.done this pm so they could keep working 4/10/2002 3:36:04 PM
|
BLD-Foundation | 4/10/2002 | 4/10/2002 | 4/10/2002 | P | PART |
Tony Young
|
|
|
foundation wall only, not int. pads 4/10/2002 3:34:19 PM
|
BLD-Footing | 4/8/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 04/08/2002 at 19:05:09. Contact: ###-####. crew has ne ftg and east half of south west ftg completed and is working on the rest arctect will be by later to sign off the rest 4/9/2002 3:00:07 PM
|