BLD-Final | 4/25/2002 | 4/26/2002 | 4/26/2002 | A | PASS |
Russ Owen
|
|
|
Scheduled by Inspector: 407 On 4/25/2002 4:42:02 PM ok perm oc. 4/26/2002 11:07:14 AM
|
Permanent Occupancy | | 4/26/2002 | 4/26/2002 | | DONE |
|
|
|
|
BLD-Final | 4/24/2002 | 4/25/2002 | 4/25/2002 | A | PART |
Russ Owen
|
|
|
JASON- ###-#### FN ok temp oc need fire caulking. 4/25/2002 4:46:05 PM
|
FIRE-Final Inspection | 4/24/2002 | 4/24/2002 | 4/24/2002 | P | PASS |
Troy Cobbley
|
|
|
fire/life safety finaled 4/24/2002 2:38:44 PM
|
BLD-Final | 4/19/2002 | 4/19/2002 | 4/19/2002 | P | CANC |
Russ Owen
|
|
|
724-*7845
|
FIRE-Final Inspection | 4/12/2002 | 4/15/2002 | 4/15/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide permits if needed for review note #1, provide annual inspection tag for fire extinguishers, provide sticker on main exit, mount and test exit/emergency lights at both basement exits, verify cfm rating of the HVAC system, install door and seal penatrations in basement 4/15/2002 10:57:17 AM
|
BLD-Framing/Rough-in | 4/12/2002 | 4/12/2002 | 4/12/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/12/2002 at 09:52:53. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/10/2002 | 4/10/2002 | 4/10/2002 | P | FAIL |
Russ Owen
|
|
|
###-#### jason New detail from the architect is ok , it indicates wraping steel beam above the 2x4 wall. As I indicated would need to be done but should have been shown on a plan detail, Yester day the detail was supposed to be on site, Owner is doing his own work and does not understand the concept of 1hr protection etc to flutes and wraping steel beam. Note: as I explained to him if he would like more explanation call his architect out to the job. 4/10/2002 1:58:01 PM
|
BLD-Framing/Rough-in | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | NR |
Russ Owen
|
|
|
###-#### jason
|
BLD-Framing/Rough-in | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | FAIL |
Russ Owen
|
|
|
###-#### . c/n posted. 4/3/2002 11:19:58 AM
|