BLD-Final | 5/10/2004 | 5/11/2004 | 5/11/2004 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/10/2004 at 1:49:51 PM. Contact: ###-####.
|
FIRE-Final Inspection | 3/31/2004 | 4/1/2004 | 4/1/2004 | A | PASS |
Rick Jackson
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore All items corrected; final okay 4/1/2004 8:34:46 AM
|
FIRE-Final Inspection | 3/15/2004 | 3/15/2004 | 3/15/2004 | P | PART |
Rick Jackson
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs Remote annunciator located in parking ramp is exposed to weather 3/15/2004 4:43:10 PM
|
BLD-Final | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | PART |
Dave Hannah
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok for temp occ 2/25/2004 12:36:07 PM
|
FIRE-Final Inspection | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | PART |
Rick Jackson
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs Per Dave Miller this will be on temp occupancy until the elevator lobby doors have the access control functions tested and approved by field inspector; the access controls will not be in use until approved 2/25/2004 1:44:33 PM
|
BLD-Final | 2/23/2004 | 2/24/2004 | 2/24/2004 | P | NR |
Dave Hannah
|
|
|
Dennis; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Final | 2/20/2004 | 2/23/2004 | 2/23/2004 | A | FAIL |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 2/20/2004 | 2/23/2004 | 2/23/2004 | A | FAIL |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 2/19/2004 | 2/20/2004 | 2/20/2004 | A | FAIL |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Final | 2/17/2004 | 2/18/2004 | 2/18/2004 | A | NR |
Dave Hannah
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
FIRE-Final Inspection | 2/17/2004 | 2/18/2004 | 2/18/2004 | A | FAIL |
Rick Jackson
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore need signs on FACP and sprinkler room doors; signs in stairwells; extinguishers in lobby and fire pump room; lobby doors can't locked to trap people in lobby area; need extinguishers in penthouse rooms and on all floors; need smoke seals on all rated doors and they must latch; need to verify emergency lighting in corridors; stairwells and exit systems must be free of construction materials; update keys in knox box; complete elevator recall/shunt and sign-off 2/18/2004 3:42:30 PM
|
BLD-Final | 2/12/2004 | 2/12/2004 | 2/12/2004 | P | NR |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore went over floor fire proofing in elec rooms 2/12/2004 4:59:38 PM
|
BLD-Final | 2/9/2004 | 2/9/2004 | 2/9/2004 | P | NR |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 2/4/2004 | 2/4/2004 | 2/4/2004 | P | PART |
Dave Hannah
|
|
|
dennis ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 1/30/2004 | 1/30/2004 | 1/30/2004 | P | DONE |
Dave Hannah
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 1/15/2004 | 1/16/2004 | 1/16/2004 | A | DONE |
Dave Hannah
|
|
|
pete ; Phone #: ###-#### Internet Inspection Request from: Annette Moore walked first floor retail 1/16/2004 11:24:26 AM
|
BLD-Framing/Rough-in | 10/28/2003 | 10/28/2003 | 10/28/2003 | P | PART |
Dave Hannah
|
|
|
6th floor nhold downs ok 10/28/2003 5:53:13 AM
|
BLD-Framing/Rough-in | 8/15/2003 | 8/15/2003 | 8/15/2003 | P | CANC |
Carl Dependahl
|
|
|
|
BLD-Conference | 8/4/2003 | 8/4/2003 | 8/4/2003 | P | PASS |
Carl Dependahl
|
|
|
re c/n...wip. 8/4/2003 4:32:04 PM
|
BLD-Framing/Rough-in | 8/1/2003 | 8/1/2003 | 8/1/2003 | P | FAIL |
Carl Dependahl
|
|
|
c/n: nuts/bolts at sw's....firestops, 8/1/2003 5:11:23 PM
|
BLD-Conference | 7/30/2003 | 7/31/2003 | 7/31/2003 | A | PASS |
Carl Dependahl
|
|
|
9:00...need r/i's for frame insp 8/1/2003 12:36:07 PM
|
BLD-Framing/Rough-in | 7/29/2003 | 7/30/2003 | 7/30/2003 | A | PART |
Carl Dependahl
|
|
|
Pete ###-####...rec'd plbg penetration details...ok.; see file at site ...PROSETS OK TO USE PVC TO CAST OR REVERSE AT 3HR DECK;RECTORSEAL AT 1HR FLOORS, 7/30/2003 12:09:06 PM
|
BLD-Framing/Rough-in | 7/30/2003 | 7/30/2003 | 7/30/2003 | P | PART |
Carl Dependahl
|
|
|
beginning hold downs...wip 7/30/2003 5:47:25 PM
|
BLD-Framing/Rough-in | 7/30/2003 | 7/30/2003 | 7/30/2003 | P | NR |
Carl Dependahl
|
|
|
W/ Leighton, Mike & Ken...need Simpson ATS details 7/30/2003 3:19:41 PM
|
BLD-Framing/Rough-in | 7/28/2003 | 7/29/2003 | 7/29/2003 | A | NR |
Carl Dependahl
|
|
|
floor sheathing...hold downs. ###-#### Pete
|
BLD-Framing/Rough-in | 7/28/2003 | 7/28/2003 | 7/28/2003 | P | PART |
Carl Dependahl
|
|
|
Pete, reviewed c/ns...wip 7/28/2003 4:28:08 PM
|
BLD-Framing/Rough-in | 7/2/2003 | 7/3/2003 | 7/3/2003 | A | NR |
Carl Dependahl
|
|
|
|
BLD-Conference | 7/2/2003 | 7/2/2003 | 7/2/2003 | A | PASS |
Carl Dependahl
|
|
|
jp, randy ,& rick re gen. exhaust termination...see nfpa 37 & nfpa 110, no determination yet, need listings. 7/2/2003 6:10:07 PM
|
BLD-Conference | 7/1/2003 | 7/1/2003 | 7/1/2003 | P | PASS |
Carl Dependahl
|
|
|
Randy; ###-####, need engs details re shear wall penetration. 7/1/2003 5:00:50 PM
|
FIRE-Conference | 7/1/2003 | 7/1/2003 | 7/1/2003 | P | PART |
Rick Jackson
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Met with Randy and Carl about the generator exhaust and it was agreed to use the stair enclosure provided it is shafted and a solid exhaust pipe 7/1/2003 3:40:34 PM
|
BLD-Framing/Rough-in | 6/30/2003 | 6/30/2003 | 6/30/2003 | P | CANC |
Carl Dependahl
|
|
|
bomb threat...unable to access site! 7/1/2003 10:36:34 AM
|
BLD-Conference | 6/25/2003 | 6/26/2003 | 6/26/2003 | A | PASS |
Carl Dependahl
|
|
|
w/ arch 11:00; need resolve plbg issues at shear & steel beam areas. 6/26/2003 12:36:52 PM
|
BLD-Conference | 6/25/2003 | 6/25/2003 | 6/25/2003 | A | CANC |
Carl Dependahl
|
|
|
11:00 w/ arch.
|
BLD-Framing/Rough-in | 6/19/2003 | 6/20/2003 | 6/20/2003 | A | PART |
Carl Dependahl
|
|
|
keep c/n....wip 6/20/2003 4:13:50 PM
|
BLD-Framing/Rough-in | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | PART |
Carl Dependahl
|
|
|
Pete...c/n issued re generic issues (fireblocking, bored studs, etc...) need eng's items addessed, wip. 6/18/2003 12:13:28 PM
|
BLD-Conference | 6/5/2003 | 6/5/2003 | 6/5/2003 | P | PASS |
Carl Dependahl
|
|
|
w/ arch, framer, drywaller, & gen contractor....need listings for pipe pens at deck, install firestopping/blocking, clarify allowable offsets for simpson thru bolt hold downs (1 3/4" max?) at detailed wall offsets (C units, ext.)...wip ok to continue.. 6/5/2003 4:16:15 PM...ok to pre install 1 side rock at court shafts. .. 6/5/2003 4:19:26 PM
|
BLD-Framing/Rough-in | 5/28/2003 | 5/28/2003 | 5/28/2003 | P | FAIL |
Carl Dependahl
|
|
|
c/n, need detail/assy for pipes at 3hr deck....cast to pvc ok?? detail shear walls: straps, blots, membrane penetrations....etc. Need eng's observation reports to date. 5/28/2003 2:59:20 PM
|
BLD-Framing/Rough-in | 5/21/2003 | 5/21/2003 | 5/21/2003 | P | PART |
Carl Dependahl
|
|
|
brg wall studs/const, east portion 5/21/2003 4:23:51 PM
|
BLD-Framing/Rough-in | 5/19/2003 | 5/19/2003 | 5/19/2003 | P | PART |
Carl Dependahl
|
|
|
randy, prelim only, wip relocating shafts against ext wall...need shear panel 1st. 5/20/2003 9:41:25 AM
|
BLD-Framing/Rough-in | 5/16/2003 | 5/16/2003 | 5/16/2003 | P | CANC |
Carl Dependahl
|
|
|
|
BLD-Conference | 5/12/2003 | 5/12/2003 | 5/12/2003 | A | PASS |
Carl Dependahl
|
|
|
W/ Bldr re c/n's 5/12/2003 1:52:36 PM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/9/2003 | 5/9/2003 | A | NR |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 5/8/2003 | 5/8/2003 | 5/8/2003 | P | CANC |
Carl Dependahl
|
|
|
|
BLD-Framing/Rough-in | 5/5/2003 | 5/8/2003 | 5/8/2003 | A | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore; prelim only, wip. 5/8/2003 4:10:37 PM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/7/2003 | 5/7/2003 | A | CANC |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 5/7/2003 | 5/7/2003 | 5/7/2003 | P | PART |
Carl Dependahl
|
|
|
prelim only; may delete joist bridging if ok by eng'r bridging 5/7/2003 4:03:40 PM
|
BLD-Framing/Rough-in | 5/5/2003 | 5/6/2003 | 5/6/2003 | A | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore: prelim. insp...will need 1hr. firestop assy detail for" top of wall" (at voids & chases) 5/6/2003 1:15:13 PM
|
BLD-Framing/Rough-in | 5/1/2003 | 5/1/2003 | 5/1/2003 | P | PART |
Carl Dependahl
|
|
|
Leighton; prelim insp only; verify all shear wall anchor bolts, stud sizing as correct, 5/1/2003 4:42:36 PM
|
BLD-Conference | 4/28/2003 | 4/29/2003 | 4/29/2003 | A | PASS |
Carl Dependahl
|
|
|
at site w supt re 1hr lids, chases, etc. 4/29/2003 12:04:14 PM
|
BLD-Framing/Rough-in | 4/27/2003 | 4/28/2003 | 4/28/2003 | A | NR |
Carl Dependahl
|
|
|
Randy
|
BLD-Framing/Rough-in | 4/28/2003 | 4/28/2003 | 4/28/2003 | P | PART |
Carl Dependahl
|
|
|
need eng's ok for "Wet" wall/shear walls...detail penetrations, blocking, drag struts, etc. 4/28/2003 5:18:22 PM
|
BLD-Conference | 4/24/2003 | 4/24/2003 | 4/24/2003 | P | PASS |
Carl Dependahl
|
|
|
w/ Randy, Steve, plbr 4/24/2003 3:43:53 PM
|
BLD-Conference | 4/22/2003 | 4/23/2003 | 4/23/2003 | A | PASS |
Carl Dependahl
|
|
|
randy & margie 9:00, reviewed corrections, submittals, etc...will propose alt fieblocking/1hr lid assy at cavity (dbl.) wall tops...26 ga steel? or? 4/23/2003 5:12:02 PM
|
BLD-Framing/Rough-in | 4/18/2003 | 4/21/2003 | 4/21/2003 | A | PART |
Carl Dependahl
|
|
|
Randy...prelim. insp, wip 4/21/2003 11:06:56 AM
|
BLD-Framing/Rough-in | 4/21/2003 | 4/21/2003 | 4/21/2003 | P | PART |
Carl Dependahl
|
|
|
wip, arch to advise re substitutions at int. sh. wall assy's 4/21/2003 5:00:16 PM
|
BLD-Framing/Rough-in | 4/18/2003 | 4/18/2003 | 4/18/2003 | P | PART |
Carl Dependahl
|
|
|
Prelim...WIP, advised re firestopping, 1hr assemblies req'd. 4/18/2003 4:38:03 PM
|
BLD-Framing/Rough-in | 4/17/2003 | 4/18/2003 | 4/18/2003 | A | CANC |
Carl Dependahl
|
|
|
|
BLD-Framing/Rough-in | 4/16/2003 | 4/18/2003 | 4/18/2003 | A | NR |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...complete gyp 4/18/2003 12:11:33 PM
|
BLD-Conference | 4/16/2003 | 4/17/2003 | 4/17/2003 | A | PART |
Carl Dependahl
|
|
|
JP Casper re insp process
|
BLD-Framing/Rough-in | 4/16/2003 | 4/17/2003 | 4/17/2003 | A | CANC |
Carl Dependahl
|
|
|
|
BLD-Framing/Rough-in | 4/17/2003 | 4/17/2003 | 4/17/2003 | P | CANC |
Carl Dependahl
|
|
|
gyp nr for reinsp 4/17/2003 10:36:14 PM
|
BLD-Framing/Rough-in | 4/16/2003 | 4/17/2003 | 4/17/2003 | A | NR |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...complete gyp install per detail at 4hr walls 4/17/2003 6:11:59 PM
|
BLD-Framing/Rough-in | 4/16/2003 | 4/16/2003 | 4/16/2003 | P | PART |
Carl Dependahl
|
|
|
Not framing, masonry insp w/ Mark, TMC...strata on structural only, will need insp at all lifts of non-struct. WIP, ok. 4/16/2003 2:05:21 PM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/16/2003 | 4/16/2003 | A | NR |
Carl Dependahl
|
|
|
Randy; still need spec onsite for 4hr wall fastening & eng'd specs for Simpson total hold-down system...stamped by Id eng'r. 4/16/2003 12:03:06 PM
|
BLD-Framing/Rough-in | 4/16/2003 | 4/16/2003 | 4/16/2003 | P | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...wip, prelim. insp, complete lev 2 shear walls & install steel cols for tomorrow? 4/16/2003 4:31:42 PM
|
BLD-Framing/Rough-in | 4/14/2003 | 4/15/2003 | 4/15/2003 | A | NR |
Carl Dependahl
|
|
|
|
BLD-Framing/Rough-in | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | FAIL |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore, c/n issued re eng'g specs for shear walls, rated assemblies thru concealed space, etc... 4/16/2003 1:57:51 PM
|
BLD-Framing/Rough-in | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | FAIL |
Carl Dependahl
|
|
|
Randy...ISI to have details/fastener schedule on hand for 4hr walls...c/n: need eng'g for simpson HD system, justification for non brg status of most of ext wall & detail fo to show FR carried thru floor lines... 4/15/2003 5:27:25 PM
|
BLD-Framing/Rough-in | 4/11/2003 | 4/14/2003 | 4/14/2003 | A | PART |
Carl Dependahl
|
|
|
prelim. only...reviewed eng's observation letter: need sister 2x4's to 3x4 studs at grid 9.4 & WB (BW5 to be 4x4)...addn of 16ga. straps at sills/plates cut for plbg req'd...replace a-bolts displaced by block-outs...need clarify 5" holes for bolts...6" spec'd (when cast, these are epoxied...) WIP 4/14/2003 3:59:21 PM
|
BLD-Framing/Rough-in | 4/14/2003 | 4/14/2003 | 4/14/2003 | P | PART |
Carl Dependahl
|
|
|
reviewed spec insp reports, need eng's ok forpossible sub-spec Field Cure samples/tests for concrete...awaiting 28 & 56 day results. 4/15/2003 11:07:34 AM May show w/ BLD02-00199 4/15/2003 11:07:56 AM
|
BLD-Concrete | 4/10/2003 | 4/11/2003 | 4/11/2003 | P | PART |
Carl Dependahl
|
|
|
masonry...to have spec. insp per supt... 4/11/2003 4:07:48 PM
|
BLD-Framing/Rough-in | 4/11/2003 | 4/11/2003 | 4/11/2003 | P | PART |
Carl Dependahl
|
|
|
WIP...prelim. struct insp. only 4/11/2003 4:55:32 PM
|
BLD-Framing/Rough-in | 4/10/2003 | 4/11/2003 | 4/11/2003 | A | CANC |
Carl Dependahl
|
|
|
|
BLD-Concrete | 4/9/2003 | 4/10/2003 | 4/10/2003 | P | NR |
Carl Dependahl
|
|
|
Masonry at retail level...Spec insp req'd?, need Fm' spec'd.; PROVIDE SPEC. INSP PER SPEC BOOK..1500Fm' reqd...MI9N4/10/2003 5:04:27 PM 4/10/2003 5:05:49 PM
|
BLD-Framing/Rough-in | 4/10/2003 | 4/10/2003 | 4/10/2003 | P | PART |
Carl Dependahl
|
|
|
PRELIMINARY WALK THRU; NEED STAMPED DETAILS & CLARIFICATION RE: 4HR WALL FRAMING (DETAIL SUBMITTED, NOT STAMPED) 4/10/2003 5:23:54 PM
|
BLD-Framing/Rough-in | 4/9/2003 | 4/10/2003 | 4/9/2003 | P | CANC |
Carl Dependahl
|
|
|
Randy
|
BLD-Conference | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | PART |
Carl Dependahl
|
|
|
rec'd MTIscope of work for epoxy anchors only... 4/9/2003 5:15:45 PM
|
BLD-Framing/Rough-in | 4/9/2003 | 4/9/2003 | 4/9/2003 | P | PART |
Carl Dependahl
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs; review frame details, prelim insp only! 4/9/2003 5:16:34 PM
|
BLD-Conference | 4/3/2003 | 4/4/2003 | 4/4/2003 | A | PASS |
Carl Dependahl
|
|
|
meet w/ ISI re 4hr walls... 4/4/2003 1:48:20 PM
|
BLD-Conference | 4/4/2003 | 4/4/2003 | 4/4/2003 | P | PASS |
Carl Dependahl
|
|
|
1:30
|
BLD-Conference | 4/3/2003 | 4/4/2003 | 4/4/2003 | A | FAIL |
Carl Dependahl
|
|
|
randy, c/n : need eng'g for steel studs, clarify shear walls...etc. 4/9/2003 7:21:16 PM
|
BLD-Conference | 4/3/2003 | 4/3/2003 | 4/3/2003 | A | PASS |
Carl Dependahl
|
|
|
randy, 8711565...need eng's comments 4/3/2003 6:15:06 PM
|
BLD-Conference | 4/3/2003 | 4/3/2003 | 4/3/2003 | A | PART |
Carl Dependahl
|
|
|
randy, 8711565
|
BLD-Framing/Rough-in | 4/2/2003 | 4/3/2003 | 4/3/2003 | A | DONE |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 4/1/2003 | 4/2/2003 | 4/2/2003 | A | PART |
Carl Dependahl
|
|
|
###-#### randuy; w/ Robb, eng'r & Leighton (framer) re wall details, insps, & order of assembly 4/2/2003 5:02:09 PM
|
BLD-Conference | 3/31/2003 | 4/1/2003 | 4/1/2003 | A | PASS |
Carl Dependahl
|
|
|
Randy...need eng's observation for 1st fl connections; keep c/n 4/1/2003 2:07:54 PM
|
BLD-Framing/Rough-in | 4/1/2003 | 4/1/2003 | 4/1/2003 | P | NR |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...need complete anchor bolt installation, will walk w/ eng'r 4-2-03 4/2/2003 5:19:48 PM...note: these are preliminary struct. frame insps only 4/2/2003 5:21:21 PM
|
BLD-Conference | 3/31/2003 | 3/31/2003 | 3/31/2003 | P | PASS |
Carl Dependahl
|
|
|
left msg for arch...need resolve eng'g insp schedule 3/31/2003 5:55:29 PM
|
BLD-Framing/Rough-in | 3/28/2003 | 3/31/2003 | 3/31/2003 | A | NR |
Carl Dependahl
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs...need eng's input & schedule re: hold-down & shear wall const, keep c/n. 3/31/2003 5:53:04 PM
|
BLD-Framing/Rough-in | 3/28/2003 | 3/28/2003 | 3/28/2003 | P | PART |
Carl Dependahl
|
|
|
pre-insp only, wip. 3/28/2003 5:23:08 PM
|
BLD-Framing/Rough-in | 3/24/2003 | 3/28/2003 | 3/28/2003 | A | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette oore...Pre-inspection, wip, need to resolve schedule/spec. insp issues. keep c/n(s) 3/28/2003 5:22:37 PM
|
BLD-Framing/Rough-in | 3/27/2003 | 3/27/2003 | 3/27/2003 | P | FAIL |
Carl Dependahl
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs, c/n...need detail for lateral support of 4hr area walls & attachments for draft stops 3/27/2003 6:37:46 PM
|
BLD-Framing/Rough-in | 3/27/2003 | 3/27/2003 | 3/27/2003 | P | CANC |
Carl Dependahl
|
|
|
Randy
|
BLD-Conference | 3/21/2003 | 3/24/2003 | 3/24/2003 | P | PASS |
Carl Dependahl
|
|
|
RANDY; Phone #: ###-#### Internet Inspection Request from: Darla Downs...keep c/n, will consult w/ PC re spec insp 3/24/2003 5:11:32 PM
|
BLD-Concrete | 3/18/2003 | 3/18/2003 | 3/18/2003 | P | PART |
Carl Dependahl
|
|
|
part, 400+yds at retail/apt occ sep. deck; need plbg sleeve info for fire ratings. pend spec insp reports
|
BLD-Conference | 3/17/2003 | 3/18/2003 | 3/18/2003 | P | PART |
Carl Dependahl
|
|
|
1:30; c/n issued to provide special insp program/eng's approval for complex eng'd wood frame features; shear walls, simpson hold-down system, approval of fire ret.treated wood & compression stacks, etc. 3/18/2003 5:34:37 PM
|
BLD-Concrete | 3/14/2003 | 3/17/2003 | 3/17/2003 | A | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...pending insp report 3/17/2003 4:33:57 PM
|
BLD-Conference | 3/13/2003 | 3/14/2003 | 3/14/2003 | P | CANC |
Carl Dependahl
|
|
|
rescheduled
|
BLD-Conference | 3/13/2003 | 3/14/2003 | 3/14/2003 | P | CANC |
Carl Dependahl
|
|
|
rescheduled
|
BLD-Concrete | 3/12/2003 | 3/13/2003 | 3/13/2003 | A | PART |
Carl Dependahl
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Annette Moore...retail roof area, pending spec insp reports 3/13/2003 4:54:59 PM
|
BLD-Conference | 3/6/2003 | 3/7/2003 | 3/7/2003 | A | NR |
Carl Dependahl
|
|
|
RANDY ###-####
|
BLD-Conference | 3/7/2003 | 3/7/2003 | 3/7/2003 | P | PASS |
Carl Dependahl
|
|
|
Randy; initial conference; will require special insp for much of wood framing...eng'r may be consulted 3/7/2003 4:58:58 PM
|
BLD-Conference | 3/5/2003 | 3/6/2003 | 3/6/2003 | P | PASS |
Carl Dependahl
|
|
|
###-#### randy ... 3/6/2003 2:00:27 PM...must encapsulate wood members at shafts 3/6/2003 4:37:37 PM
|