BLD-Final | 12/9/2002 | 12/10/2002 | 12/10/2002 | P | PASS |
Carl Dependahl
|
|
|
curt ###-####
|
BLD-Final | 12/9/2002 | 12/9/2002 | 12/9/2002 | P | FAIL |
Carl Dependahl
|
|
|
###-#### CURT PLEASE CALL 1ST...need elecc interconnect for detectors working.. 12/9/2002 4:15:11 PM
|
BLD-Conference | 12/6/2002 | 12/6/2002 | 12/6/2002 | A | PASS |
Carl Dependahl
|
|
|
all htg passed...interconnect detectors 12/6/2002 11:00:09 AM
|
BLD-Final | 12/4/2002 | 12/5/2002 | 12/5/2002 | A | NR |
Carl Dependahl
|
|
|
call 1st before insp -kirt; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...need all mech permits finalled, notified owner. 12/5/2002 9:11:25 AM
|
BLD-Conference | 5/31/2002 | 5/31/2002 | 5/31/2002 | A | PASS |
Carl Dependahl
|
|
|
need stamp on eng's detail for int chimney....has detail; install rails at rear ext. landing per 1003
|
BLD-Energy code compliance | 5/31/2002 | 5/31/2002 | 5/31/2002 | P | PART |
Carl Dependahl
|
|
|
###-####- ryan... floor area sheathed, upper deck floor insulated 5/31/2002 12:09:45 PM
|
BLD-Framing/Rough-in | 5/16/2002 | 5/17/2002 | 5/17/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 17:49:47. Contact: ###-####. eng letter with plans 5/20/2002 7:37:52 AM
|
BLD-Framing/Rough-in | 5/15/2002 | 5/16/2002 | 5/16/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/15/2002 at 16:32:36. Contact: ###-####. garage area ok; awaiting engs report for truss/ shearwall connections & configuration...dont cover mstr bath / bedrm area until engr ok's; Also, interior "chimney" req's eng's design or construct per UBC w/ rebar, etc...chimney is extension of lower floor flue...flue req's support. 5/16/2002 4:38:46 PM
|
BLD-Energy code compliance | 5/13/2002 | 5/14/2002 | 5/14/2002 | A | PART |
Carl Dependahl
|
|
|
###-#### RYAN FRAMING R/I AS WELL hr walls 5/14/2002 11:23:01 AM keep c/n, eng'r to walk-thru...add'l c/n re masonry chimney ties. 5/14/2002 12:54:20 PM
|
BLD-Framing/Rough-in | 5/14/2002 | 5/14/2002 | 5/14/2002 | A | PART |
Carl Dependahl
|
|
|
garage & hse reinsp-frame...need eng's report/approval for drag strut truss: install roof/clg ties for masonry chimney extensions...do not cover that area; gar, main floor & library ok to cover.
|
BLD-Energy code compliance | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/10/2002 at 13:42:33. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/10/2002 at 13:43:11. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/13/2002 | 5/13/2002 | 5/13/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by Inspector: 407 On 5/13/2002 1:16:05 PM
|
BLD-Framing/Rough-in | 5/7/2002 | 5/7/2002 | 5/7/2002 | P | PART |
Tony Young
|
|
|
fr ryan ###-#### re-insp
c/n still posted,,, ok to insulate house only 5/7/2002 2:06:17 PM
|
BLD-Framing/Rough-in | 5/3/2002 | 5/6/2002 | 5/6/2002 | A | NR |
Carl Dependahl
|
|
|
###-####
|
BLD-Framing/Rough-in | 5/3/2002 | 5/6/2002 | 5/6/2002 | A | NR |
Carl Dependahl
|
|
|
recall 5/6/2002 9:22:25 AM
|
BLD-Framing/Rough-in | 5/6/2002 | 5/6/2002 | 5/6/2002 | P | FAIL |
Carl Dependahl
|
|
|
###-#### RYAN c/n , air seal , fireblocks, straps, need eng's ok for modifications (int shearwall/truss connection & othe 5/6/2002 6:29:03 PM s 5/6/2002 6:29:12 PM
|
BLD-Framing/Rough-in | 5/2/2002 | 5/3/2002 | 5/3/2002 | P | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/02/2002 at 12:53:31. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/30/2002 | 5/1/2002 | 5/1/2002 | A | PART |
Dave Hannah
|
|
|
shear insp carl did inspection 5/1/2002 10:41:05 AM
|
BLD-Framing/Rough-in | 5/1/2002 | 5/1/2002 | 5/1/2002 | P | PART |
Carl Dependahl
|
|
|
ok to side only, need eng'g. ext. nailing ok only.
|
BLD-Framing/Rough-in | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | PART |
Carl Dependahl
|
|
|
SHEER NAIL ###-#### RYAN
|
BLD-Framing/Rough-in | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | NR |
Carl Dependahl
|
|
|
###-#### RYAN ADD HDWE. PER ENG'G, RECALL 4/29/2002 9:08:22 AM
|
BLD-Conference | 4/22/2002 | 4/23/2002 | 4/23/2002 | A | PASS |
Carl Dependahl
|
|
|
###-####- RYAN consult P&Z, plan chk for permit for garage modification...this is a separate bldg from house remodel 4/23/2002 11:47:58 AM
|
BLD-Footing | 3/20/2002 | 3/21/2002 | 3/21/2002 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 03/20/2002 at 16:55:11. Contact: ###-####. Footing appears within min. setb 3/21/2002 10:09:13 AM
|
BLD-Footing | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | FAIL |
Carl Dependahl
|
|
|
###-#### RYAN ; need soils test, min. 1500 psf per eng'd plans...appears to be some clay type soils w/ much organic mat'l. Also, need complete set approved plans 3/15/2002 9:40:23 AM
|