Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD02-00505
StatusFinaled
Name ROMAN CATHOLIC DIOCE SE
Site Address 825 W FORT ST
Project NameST JOSEPH'S SCHOOL
Customer Number 
ePlanReviewNo
Description
St. Joseph's School * To construct a two story, Type V 1hr classroom addition between the existing classrooms and gym. Includes (5) class room, media ctr. expansion, stor room, new ramp, and a elevator. Materials will match the existing building w/brick and strucco and windows, wd trim will match adjacent finishes. Entire building will receive a new fire sprinklers system throughout which will be used for substitution of one-hour construction. Fire Sprinkler and Fire Alarm require seperate permitting and approval, as regulated by the Fire Chief. All work is per approved plans and attachments RH01-00243. Area of the addition is 3, 429.5 square feet for the 1st and 2nd floors with a total of 6,859 sq. ft.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference10/18/200210/18/200210/18/2002PPASS
DetailsWm. Michael Meloy
Compliant with DRH01-00243 10/18/2002 1:40:55 PM
Permanent Occupancy 10/18/200210/18/2002 DONE
Details
BLD-Conference10/11/200210/15/200210/15/2002APASS
DetailsCarl Dependahl
Mike ; 10/15/02 9:53:06 AM Need verify P&Z, for perm c/o; called contractor...project isn't finalled. 10/15/02 9:54:44 AM
BLD-Conference10/4/200210/7/200210/7/2002ACANC
DetailsCarl Dependahl
BLD-Conference10/2/200210/3/200210/3/2002PNH
DetailsCarl Dependahl
Call Mike
BLD-Conference10/1/200210/2/200210/2/2002ANR
DetailsCarl Dependahl
Call Mike
BLD-Final9/29/200210/1/200210/1/2002ANR
DetailsCarl Dependahl
unable to contact 10/1/2002 6:25:51 PM
BLD-Final9/20/20029/23/20029/23/2002ANR
DetailsCarl Dependahl
wanted pm 9/23/2002 11:35:43 AM
BLD-Final9/23/20029/23/20029/23/2002PNR
DetailsCarl Dependahl
###-#### call Mike prior to going ...need card w/ sig's of p&z 9/29/2002 3:41:59 PM
BLD-Final9/23/20029/23/20029/23/2002PFAIL
DetailsCarl Dependahl
need verify p&z ok, ok for t/o... 9/23/2002 12:04:54 PM
BLD-Final9/18/20029/18/20029/20/2002PNR
DetailsCarl Dependahl
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie called,no answer 9/20/2002 6:40:47 PM 9/20/2002 6:41:16 PM
BLD-Final9/17/20029/17/20029/17/2002PFAIL
DetailsJim Sly
###-#### Called Mike, notified of Ele02-02750 permit for elevator ....outstanding Will call for final 9/18/02 am. 9/17/2002 1:44:01 PM
BLD-Final9/11/20029/11/20029/11/2002PNR
DetailsTom Arcoraci
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs public works and code enforce to sign 9/11/2002 3:22:42 PM
BLD-Final9/4/20029/4/20029/4/2002PNR
DetailsCarl Dependahl
colin; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...need elec final for elev...verify last structural items 9/4/2002 2:34:49 PM
FIRE-Final Inspection9/3/20029/3/20029/3/2002PPASS
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
FIRE-Final Inspection8/26/20028/23/20028/26/2002PPART
DetailsRick Jackson
okat to occupy the first floor of the new addition and exsisting school portion; second floor of new addition will require another inspection prior to occupancy
BLD-Framing/Rough-in8/22/20028/22/20028/22/2002PPART
DetailsJim Storey
MIKE; Phone #: ###-####ceillings ok 2nd floor/ need 26 gage duct on smoke evacuation system/ fire tape above grid in storage rm to maintane 1 hr occ./ 8/22/2002 3:18:03 PM
BLD-Conference8/20/20028/20/20028/20/2002PPASS
DetailsCarl Dependahl
1st fl only ok to finish...obtain partial c/o or t/o for occupancy, consult fire insp.
FIRE-Conference8/19/20028/19/20028/19/2002PPART
DetailsRick Jackson
met with Mike of JW; told him they would have to get approval for temp occupancy from Steve Minnis as Dave Miller is gone all week
BLD-Framing/Rough-in8/15/20028/15/20028/15/2002PPART
DetailsCarl Dependahl
###-#### mike , grid ok...add some spreaders as needed; firestop vent pipe at SE corner lid in "lab"; 1st fl ok for cover pend fire r/i. 8/15/2002 3:49:25 PM
BLD-Framing/Rough-in7/25/20027/25/20027/25/2002PPART
DetailsTom Arcoraci
mike; Phone #: ###-#### ok to cover over glass pipes both floors 7/25/2002 2:29:09 PM
BLD-Framing/Rough-in7/24/20027/24/20027/24/2002PPART
DetailsDave Hannah
mike ; Phone #: ###-#### 1st floor only ok to cover all but for around gas piping still needs to shoe studs 7/24/2002 4:06:46 PM
FIRE-Conference7/22/20027/22/20027/22/2002PPART
DetailsRick Jackson
met with Mike (GC) and reviewed project and told him they need to get a letter ready for Dave Miller for them get approval to occupy the retrofit area of the old portion of the school. Alarms will have to work and exiting 7/22/2002 3:51:25 PM
BLD-Framing/Rough-in7/17/20027/18/20027/18/2002APART
DetailsCarl Dependahl
Mike, reinsp....ok to "pre rock"...complete ext . nailing at blocked edges, fireblocking; ok to insulate. Need Fire sprinkler r/i...prior to complete frame sign-off. 7/18/2002 11:04:08 AM
BLD-Framing/Rough-in7/16/20027/17/20027/17/2002PNR
DetailsCarl Dependahl
mike; Phone #: ###-####, keep c/n. 7/17/2002 3:43:16 PM
BLD-Framing/Rough-in7/12/20027/15/20027/15/2002AFAIL
DetailsCarl Dependahl
FR INSP- MIKE ###-#### c/n onsite, reca 7/15/2002 12:13:43 PM ll 7/15/2002 12:15:34 PM
BLD-Framing/Rough-in7/11/20027/12/20027/12/2002ANR
DetailsCarl Dependahl
fr mike- ###-####
BLD-Framing/Rough-in7/12/20027/12/20027/12/2002PNR
DetailsCarl Dependahl
BLD-Framing/Rough-in7/12/20027/12/20027/12/2002ACANC
DetailsCarl Dependahl
###-####
BLD-Framing/Rough-in7/12/20027/12/20027/12/2002PCANC
DetailsCarl Dependahl
###-####; St Johns school
BLD-Conference6/24/20026/25/20026/25/2002APART
DetailsCarl Dependahl
framing wip; rec'd MTI soils report 6/25/2002 9:02:42 AM
BLD-Conference6/10/20026/10/20026/10/2002PPASS
DetailsCarl Dependahl
w/ arch & cont at site re 1hr elev...looked at floor joisting...may need addl nails for diaphragm straps.
BLD-Concrete6/3/20026/4/20026/4/2002APART
DetailsCarl Dependahl
chk on spec insp for fnd; has to run drainage to outside of bldg (seepage pit?)...dicussed elev shaft const. w/ arch. 6/4/2002 10:43:06 AM & supt. 6/4/2002 10:43:21 AM
BLD-Conference5/14/20025/14/20025/14/2002PPASS
DetailsCarl Dependahl
pre-con mtg re spec insp, plan req's, etc
BLD-Footing5/14/20025/14/20025/14/2002PPART
DetailsCarl Dependahl
###-#### MIKE ; ftgs ok pend MTI report 5/14/2002 2:55:31 PM