BLD-Final | 7/24/2002 | 7/24/2002 | 7/24/2002 | P | PASS |
Steven Webb
|
|
|
pj smith- ###-#### fn C. of C. #23290 issued. 7/24/2002 3:28:28 PM
|
BLD-Energy code compliance | 5/1/2002 | 5/2/2002 | 5/2/2002 | A | FAIL |
Dave Hannah
|
|
|
###-#### PJ c/n items not complete on framing 5/2/2002 10:11:50 AM
|
BLD-Energy code compliance | 5/2/2002 | 5/2/2002 | 5/2/2002 | P | PASS |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 5/2/2002 1:18:09 PM
|
BLD-Energy code compliance | 4/29/2002 | 4/30/2002 | 4/30/2002 | A | NR |
Steven Webb
|
|
|
###-#### PJ
|
BLD-Framing/Rough-in | 4/26/2002 | 4/29/2002 | 4/29/2002 | A | PART |
Steven Webb
|
|
|
###-#### pj c/n posted--ok to insulate. 4/29/2002 10:38:10 AM
|
BLD-Framing/Rough-in | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | PART |
Steven Webb
|
|
|
SHEER WALL ###-#### PJ Ok to cover 4/24/2002 11:13:20 AM
|
BLD-Conference | 4/23/2002 | 4/23/2002 | 4/23/2002 | P | DONE |
Steven Webb
|
|
|
Scheduled by Inspector: 420 On 4/23/2002 2:31:47 PM Talked to permit holder (P. J. Smith) via phone--house is 3/4 complete with siding-no shear inspection has occurred. Marked on approved plans which panels need to be removed to allow inspection. Placed red "Do Not Cover" sticker on outside. Also to post address. 4/23/2002 2:34:30 PM 4/23/2002 2:36:10 PM
|
BLD-Foundation | 4/1/2002 | 4/1/2002 | 4/1/2002 | P | PART |
Steven Webb
|
|
|
###-#### JIM wip--75% ready at time of inspection 4/1/2002 1:29:43 PM
|
BLD-Footing | 3/29/2002 | 3/29/2002 | 3/29/2002 | P | PART |
Steven Webb
|
|
|
###-#### dirk wip--20% ready at time of inspection. 3/29/2002 2:27:22 PM
|
BLD-Footing | 3/27/2002 | 3/27/2002 | 3/27/2002 | P | NR |
Dave Hannah
|
|
|
###-#### hole dug no one on site no forms no plans ect 3/27/2002 3:32:46 PM
|