BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Tony Young
|
|
|
fn ###-####
|
BLD-Energy code compliance | 5/8/2002 | 5/9/2002 | 5/9/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 14:52:22. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/8/2002 | 5/9/2002 | 5/9/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 14:51:26. Contact: ###-####. c/n made ok 5/9/2002 11:46:10 AM
|
BLD-Energy code compliance | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/08/2002 at 10:41:00. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/8/2002 | 5/8/2002 | 5/8/2002 | P | NR |
Jim Storey
|
|
|
1. RISE AND RUN - The rise of steps shall not be less than 4 inches or greater than 8 inches. The run shall not be less than 9 inches as measured horizontally between the vertical planes of the furthermost projection of adjacent treads. The largest tread run within a flight of stairs shall not exceed the smallest by more than 3/8 inch. The greatest riser height within any flight of stairs shall not exceed the smallest by more than 3/8 inch. (1997 UBC 1003.3.3.3 and Exception #1)
|
BLD-Framing/Rough-in | 5/7/2002 | 5/7/2002 | 5/7/2002 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 05/07/2002 at 08:04:53. Contact: ###-####. C/N Stair run not code compliant. 5/7/2002 4:34:46 PM
|
BLD-Framing/Rough-in | 4/29/2002 | 4/30/2002 | 4/30/2002 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/29/2002 at 14:44:19. Contact: ###-####...complete c/n. 4/30/2002 11:06:13 AM
|
BLD-Framing/Rough-in | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/30/2002 at 09:51:54. Contact: ###-####. ext shear walls, truss blocks at sw6 ok, c/n ok. 4/30/2002 5:12:20 PM
|
BLD-Framing/Rough-in | 4/29/2002 | 4/29/2002 | 4/29/2002 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/29/2002 at 07:00:19. Contact: ###-####.c/n posted. 4/29/2002 11:50:03 AM
|
BLD-Foundation | 4/9/2002 | 4/10/2002 | 4/10/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 06:50:27. Contact: ###-####. walls ok 4/10/2002 5:11:49 PM
|
BLD-Footing | 4/9/2002 | 4/9/2002 | 4/9/2002 | P | PART |
Carl Dependahl
|
|
|
for strap- ###-#### ft -re-insp..set backs appear ok, strung 1 side; show wall steel at fnd insp 4/9/2002 2:58:26 PM
|
BLD-Footing | 4/9/2002 | 4/9/2002 | 4/9/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 06:48:34. Contact: ###-####. install steel, show p.lines. 4/9/2002 1:26:32 PM
|