BLD-Final | 10/1/2002 | 10/2/2002 | 10/2/2002 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Grading Inspection | 10/1/2002 | 10/1/2002 | 10/1/2002 | | BOND |
Rita DeYoung
|
|
|
Grading and drainage is complete. Revegetation must be completed on this lot and disturbed areas of lots to the south and west. Grading is conditionally approved upon receipt of $500.00 bond for revegetation.
|
BLD-Final | 9/27/2002 | 9/30/2002 | 9/30/2002 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 09/27/2002 at 15:40:23. Contact: ###-####.c/n posted 9/30/2002 4:54:47 PM
|
BLD-Energy code compliance | 7/17/2002 | 7/18/2002 | 7/18/2002 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/17/2002 at 16:17:19. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/17/2002 | 7/18/2002 | 7/18/2002 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/17/2002 at 16:16:20. Contact: ###-####.
|
BLD-Conference | 7/12/2002 | 7/12/2002 | 7/12/2002 | P | PASS |
Carl Dependahl
|
|
|
has new energy calcs...ok to insul to spec; keep c/n.
|
BLD-Framing/Rough-in | 7/9/2002 | 7/11/2002 | 7/11/2002 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 07/09/2002 at 14:29:17. Contact: ###-####. c/n: straps, fireblox, vapor barriers, Insulation values to be shown prior to install (new mec check or?...reqs r-19 walls 7/11/2002 4:36:49 PM
|
BLD-Framing/Rough-in | 7/2/2002 | 7/10/2002 | 7/9/2002 | P | CANC |
Tony Young
|
|
|
GRANT ###-#### Disp set to [CANC] by a contractor via Hello! on 07/09/2002 at 14:31:29.
|
BLD-Framing/Rough-in | 7/1/2002 | 7/2/2002 | 7/2/2002 | P | FAIL |
Tony Young
|
|
|
grant ###-#### SHEER NAIL
c/n posted, exterior sheer. 7/2/2002 2:30:06 PM
|
BLD-Footing | 5/23/2002 | 5/24/2002 | 5/24/2002 | A | PART |
Tony Young
|
|
|
GREG ###-####
int. slab ftgs, already poured 5/24/2002 12:15:54 PM
|
BLD-Foundation | 5/14/2002 | 5/15/2002 | 5/15/2002 | A | PART |
Carl Dependahl
|
|
|
jim ###-#### found wall...ok, chk point load ftgs at slab prior to next pour 5/15/2002 5:14:02 PM
|
BLD-Footing | 5/9/2002 | 5/10/2002 | 5/10/2002 | A | PART |
Tony Young
|
|
|
poured w/ out inspection due to inspector could not make on prior day when it was called in for,// contractor said he was not notified and did not see any thing onsite and assumed he was ok////verify width and depth and setbacks when we inspect walls. 5/10/2002 12:54:50 PM
|
BLD-Grading Inspection | 5/10/2002 | 5/10/2002 | 5/10/2002 | | DONE |
Rita DeYoung
|
|
|
Geotechnical engineer has approved footing subgrade
|
BLD-Footing | 5/9/2002 | 5/9/2002 | 5/9/2002 | P | CANC |
Jim Storey
|
|
|