BLD-Final | 1/6/2003 | 1/7/2003 | 1/7/2003 | A | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/06/2003 at 14:53:34. Contact: ###-####....elec finalled, ok 1/7/2003 9:17:38 AM
|
BLD-Final | 6/11/2002 | 6/11/2002 | 6/11/2002 | P | PART |
Carl Dependahl
|
|
|
BOB ###-####
|
BLD-Framing/Rough-in | 6/11/2002 | 6/11/2002 | 6/11/2002 | P | PART |
Carl Dependahl
|
|
|
rec'd truss calcs
|
BLD-Final | 6/10/2002 | 6/10/2002 | 6/10/2002 | P | NR |
Carl Dependahl
|
|
|
robert- ###-#### fn need truss calcs for struct final. 6/10/2002 3:17:13 PM
|
BLD-Framing/Rough-in | 6/10/2002 | 6/10/2002 | 6/10/2002 | P | PART |
Carl Dependahl
|
|
|
cut attic access....show beams per plans at car port; reinspect hdr at "shed"....header ok, need truss calcs , ok to continue. 6/10/2002 3:16:49 PM
|
BLD-Final | 6/7/2002 | 6/7/2002 | 6/7/2002 | P | FAIL |
Carl Dependahl
|
|
|
fn bob- ###-####...add header at brg wall; owner says P&Z approver set back? 6/7/2002 4:19:30 PM
|
BLD-Foundation | 5/1/2002 | 5/1/2002 | 5/1/2002 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 08:35:50. Contact: ###-####. ftg prev. ok'd, sits close to p/l (fence on plans?) called GS 5/1/2002 3:46:29 PM
|
BLD-Footing | 4/24/2002 | 4/25/2002 | 4/25/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/24/2002 at 19:29:01. Contact: ###-####.
|