BLD-Final | 7/25/2002 | 7/26/2002 | 7/26/2002 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 07/25/2002 at 12:04:26. Contact: ###-####. c.c # 7/26/2002 1:57:21 PM 17612 issued 7/26/2002 1:57:33 PM
|
BLD-Final | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | NH |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 07/24/2002 at 14:44:24. Contact: ###-####. No access-phoned contact no answer-left message to recall. 7/25/2002 12:09:03 PM
|
BLD-Energy code compliance | 6/12/2002 | 6/13/2002 | 6/13/2002 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/12/2002 at 11:09:41. Contact: ###-####. Cancelled by contractor 6/12/2002 3:33:11 PM
|
BLD-Framing/Rough-in | 6/12/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Steven Webb
|
|
|
fr insp jake- ###-#### Ok to insulate 6/13/2002 2:45:36 PM
|
BLD-Framing/Rough-in | 6/11/2002 | 6/12/2002 | 6/12/2002 | P | PART |
Steven Webb
|
|
|
fr jake- ###-#### C/N-Ok to insulate. 6/12/2002 1:55:29 PM
|
BLD-Other | 6/6/2002 | 6/7/2002 | 6/7/2002 | A | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 06/06/2002 at 15:08:03. Contact: ###-####. SHEAR--ok to side 6/7/2002 12:01:07 PM
|
BLD-Foundation | 5/22/2002 | 5/22/2002 | 5/22/2002 | P | PART |
Steven Webb
|
|
|
found wall wes -###-#### wip--85% ready 5/22/2002 3:35:23 PM
|
BLD-Footing | 5/21/2002 | 5/21/2002 | 5/21/2002 | P | PART |
Steven Webb
|
|
|
ft wesley ###-#### 75% ready 5/21/2002 2:26:39 PM
|