Permanent Occupancy | | 10/16/2003 | 10/16/2003 | | DONE |
|
|
|
|
BLD-Final | 9/19/2002 | 9/20/2002 | 9/20/2002 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung Should have been PM insp. 9/20/2002 9:27:53 AM
|
BLD-Final | 9/20/2002 | 9/20/2002 | 9/20/2002 | P | PASS |
Tom Arcoraci
|
|
|
FN INSP -DAVE 890- ok for perm 9/20/2002 3:19:53 PM
|
FIRE-Final Inspection | 9/19/2002 | 9/19/2002 | 9/19/2002 | P | PART |
Troy Cobbley
|
|
|
temporary occupancy given until the fire alarm system for the entire building has been upgraded. Per a letter to dave miller with the boise fire dept this is to be completed in 90 days
|
BLD-Framing/Rough-in | 9/13/2002 | 9/13/2002 | 9/13/2002 | P | PASS |
Russ Owen
|
|
|
###-#### dave
|
FIRE-Final Inspection | 9/12/2002 | 9/12/2002 | 9/12/2002 | A | PART |
Troy Cobbley
|
|
|
Hood system tested OK. Fire sprinklers OK
|
BLD-Framing/Rough-in | 8/27/2002 | 8/28/2002 | 8/28/2002 | A | CANC |
Russ Owen
|
|
|
one hour shaft . need to complete to flutes. 8/28/2002 12:08:54 PM
|
FIRE-Conference | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | DONE |
Troy Cobbley
|
|
|
met with contractor and went over life/safety notes 8/28/2002 8:02:44 AM
|