BLD-Final | 12/12/2002 | 12/13/2002 | 12/13/2002 | A | PASS |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok perm oc. 12/13/2002 9:57:07 AM
|
Permanent Occupancy | | 12/13/2002 | 12/13/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/11/2002 | 12/12/2002 | 12/12/2002 | A | PASS |
Troy Cobbley
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
FIRE-Conference | 11/12/2002 | 11/12/2002 | 11/12/2002 | A | DONE |
Troy Cobbley
|
|
|
I spoke to Jim with Steed Construction and notified him that the temp occ. for this project expires next wednesday
|
BLD-Final | 8/16/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 08/16/2002 at 15:03:25. Contact: ###-####.OK temp oc.pending all signatures. 8/19/2002 4:13:33 PM
|
FIRE-Alarm Testing | 8/16/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Troy Cobbley
|
|
|
temporary occupancy given until the fire alarm system is complete 8/19/2002 3:39:50 PM
|
FIRE-Final Inspection | 8/16/2002 | 8/19/2002 | 8/19/2002 | P | PART |
Troy Cobbley
|
|
|
life safety items complete. Temp occupancy given until the fire alarm is complete 8/19/2002 3:40:33 PM
|
FIRE-Alarm Testing | 8/15/2002 | 8/16/2002 | 8/16/2002 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 8/16/2002 1:49:44 PM
|
FIRE-Final Inspection | 8/15/2002 | 8/16/2002 | 8/16/2002 | P | FAIL |
Troy Cobbley
|
|
|
remove thumbturn and key hardware from the ware house door, provide additional fire extinguisher in warehouse, finish connection of duct smoke detectors. Dave Miller gave permission for temp occ as long as fire alarm plans had been submitted 8/16/2002 2:31:24 PM
|
FIRE-Supply Line Hydro | 8/15/2002 | 8/16/2002 | 8/16/2002 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 8/16/2002 1:49:36 PM 8/16/2002 1:50:01 PM
|
FIRE-Final Inspection | 8/6/2002 | 8/7/2002 | 8/7/2002 | A | CANC |
Troy Cobbley
|
|
|
jim ###-#### the fire sprinkler correction notice has not been taken care of yet 8/7/2002 3:53:18 PM
|
BLD-Wall cover | 7/16/2002 | 7/16/2002 | 7/16/2002 | P | PASS |
Russ Owen
|
|
|
jim enzler; Phone #: ###-####ok grid ceiling. 7/16/2002 5:19:33 PM
|
BLD-Wall cover | 7/11/2002 | 7/12/2002 | 7/12/2002 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 07/11/2002 at 11:40:38. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/21/2002 | 6/21/2002 | 6/21/2002 | P | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/21/2002 at 09:11:53. Contact: ###-####.ok to cover pending other trades.Ele and mec.Called contractor and notifed. 6/21/2002 4:29:22 PM 6/21/2002 4:33:13 PM
|
BLD-Framing/Rough-in | 6/19/2002 | 6/19/2002 | 6/19/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 06/19/2002 at 08:28:48. Contact: ###-####.wanted to cover a portion of wall but , needs electrical prior. 6/19/2002 5:05:22 PM
|