BLD-Final | 12/8/2003 | 12/9/2003 | 12/9/2003 | A | PASS |
Jim Storey
|
|
|
karen or jerry; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
Permanent Occupancy | | 12/8/2003 | 12/8/2003 | | DONE |
|
|
|
|
BLD-Final | 12/1/2003 | 12/3/2003 | 12/3/2003 | A | PASS |
Jim Storey
|
|
|
remove fire door door stops. c/n made ok/ please mail co to tenent. 12/8/2003 4:19:49 PM
|
BLD-Aging Inspection | 12/1/2003 | 12/1/2003 | 12/1/2003 | | NR |
Jim Storey
|
|
|
check back on wed. cloned. for final. 12/1/2003 1:46:42 PM
|
FIRE-Final Inspection | 10/1/2003 | 10/1/2003 | 10/1/2003 | P | PASS |
Rick Jackson
|
|
|
fire alarms completed; elevator recall not completed due to old elevator controller and this was approved by Dave Miller; elevator recall will be provided if the controller is replaced 10/1/2003 4:42:50 PM
|
BLD-Aging Inspection | 9/8/2003 | 9/8/2003 | 9/8/2003 | | FAIL |
Jim Storey
|
|
|
sam rogers notafied will check with dave miller. 9/8/2003 3:12:06 PM
|
BLD-Aging Inspection | 7/9/2003 | 7/9/2003 | 7/9/2003 | | PASS |
Jim Storey
|
|
|
recieved info from jerry beto defered to sam and david miller based on millers letter. 7/9/2003 8:24:09 AM
|
BLD-Aging Inspection | 4/18/2003 | 4/21/2003 | 4/21/2003 | A | PART |
Rick Jackson
|
|
|
help ! thanks j.storey talked to Sam Rogers and he said Phil Omas had sent him a request on info about supervisory/trouble signals from the alarm panel (see history); I called Phil Omas and he said he was working on getting a quote for the work to the owner and should have one to the owner in a few days; called Phil of Contracting Unlimited and told him about this info 4/22/2003 10:07:46 AM
|
BLD-Aging Inspection | 4/18/2003 | 4/18/2003 | 4/18/2003 | | NR |
Jim Storey
|
|
|
sent to 409 4/18/2003 8:58:25 AM
|
FIRE-Final Inspection | 10/23/2002 | 10/24/2002 | 10/24/2002 | A | FAIL |
Rick Jackson
|
|
|
###-#### need alarm plans as per fire review notes; panel needs smoke detector; 60 hr batteries; knox box needed as panel reports off-site; temp occ will need to be approved by Dave Miller 10/24/2002 12:35:53 PM
|
FIRE-Conference | 9/18/2002 | 9/18/2002 | 9/18/2002 | P | PART |
Rick Jackson
|
|
|
met with GC while doing a sprinkler rough in; fire plan review notes indicated fire alarm plans were needed; checked alarm panel and it requires smoke detector above panel and 60 hour of batteries; the building is sprinklered and requires off site monitoring; the building has pull stations and the old style strobes with red lenses (not compliant with ADA) and horns; this tenant has several AHU's that appear to require detectors for shutdown (common plenum and no mechanical plans)
|
BLD-Framing/Rough-in | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PASS |
Jim Storey
|
|
|
PHIL; Phone #: ###-####
|