BLD-Final | 2/12/2003 | 2/13/2003 | 2/13/2003 | P | PASS |
Tony Young
|
|
|
###-####,,, l of c issued 2/13/2003 2:53:38 PM
|
BLD-Grading Inspection | 2/12/2003 | 2/12/2003 | 2/12/2003 | | BON |
Rita DeYoung
|
|
|
rough grading and roof drain connection are complete. Fine grading and revegetation are not complete. For this the engineer has recommended a $650.00 bond. Upon receipt of this the grading and drainage are conditionally approved.
|
BLD-Final | 2/10/2003 | 2/11/2003 | 2/11/2003 | P | FAIL |
Tony Young
|
|
|
BIG AL ###-####
c/n posted, hung on elec. panel 2/11/2003 1:49:24 PM
|
BLD-Energy code compliance | 11/18/2002 | 11/19/2002 | 11/19/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/18/2002 at 13:12:44. Contact: ###-####.OK TO COVER AFTER YOU TIGHTEN HOLD DOWNS 11/19/2002 11:36:26 AM
|
BLD-Framing/Rough-in | 11/12/2002 | 11/13/2002 | 11/13/2002 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/12/2002 at 09:21:19. Contact: ###-####.c/n posted, ok to insulate 11/13/2002 2:07:13 PM
|
BLD-Framing/Rough-in | 10/17/2002 | 10/18/2002 | 10/18/2002 | A | PART |
Jim Sly
|
|
|
SHEER ###-#### ALAN Shear OK. 10/18/2002 12:40:53 PM
|
BLD-Foundation | 8/26/2002 | 8/26/2002 | 8/26/2002 | P | PASS |
Dave Hannah
|
|
|
jim; Phone #: ###-####
|
BLD-Grading Inspection | 8/26/2002 | 8/26/2002 | 8/26/2002 | | DONE |
Rita DeYoung
|
|
|
Lower footing subgrade has been approved by the geotechnical engineer.
|
BLD-Footing | 8/21/2002 | 8/22/2002 | 8/22/2002 | A | PART |
Tony Young
|
|
|
###-####
ok to pour upper ftgs 8/22/2002 10:35:06 AM
|
BLD-Grading Inspection | 8/22/2002 | 8/22/2002 | 8/22/2002 | | DONE |
Rita DeYoung
|
|
|
Geotechnical engineer indicates the subgrade for the upper footings is ok. However, lower footing subgrade is soft and must be replaced with structural fill.
|