BLD-Aging Inspection | 5/2/2005 | 5/2/2005 | 5/2/2005 | | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 5/2/2005 | 5/2/2005 | 5/2/2005 | P | PASS |
Jim Storey
|
|
|
l/c isued downtown
|
BLD-Final | 12/11/2002 | 12/12/2002 | 12/12/2002 | A | PASS |
Russ Owen
|
|
|
###-####. ok for perm oc. 12/12/2002 11:37:50 AM
|
FIRE-Final Inspection | 12/10/2002 | 12/11/2002 | 12/11/2002 | A | PASS |
Troy Cobbley
|
|
|
ok for perm occupancy 12/11/2002 12:44:30 PM
|
FIRE-Final Inspection | 12/4/2002 | 12/5/2002 | 12/5/2002 | P | CANC |
Troy Cobbley
|
|
|
cancelled by Jim with Steed construction 12/5/2002 4:07:36 PM
|
FIRE-Final Inspection | 12/2/2002 | 12/2/2002 | 12/2/2002 | P | FAIL |
Troy Cobbley
|
|
|
smoke exhaust system does not operate correctly. The louver appears to be stuck 12/2/2002 4:27:37 PM
|
BLD-Final | 10/4/2002 | 10/4/2002 | 10/4/2002 | P | PART |
Russ Owen
|
|
|
ok temp oc , c/n handrail step riser. 10/4/2002 1:49:33 PM
|
FIRE-Final Inspection | 10/3/2002 | 10/4/2002 | 10/4/2002 | P | CANC |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
FIRE-Final Inspection | 10/3/2002 | 10/4/2002 | 10/4/2002 | A | PART |
Troy Cobbley
|
|
|
temporary occupancy given on the fire life/safety and the fire alarm per dave miller's permission until the fire alarm drawings are approved and the system tested. the fire sprinklers are finaled and life/safety is finaled. I notified the contractor that hardware on several doors needed changed. He made the phone call to the supplyer while I was there. Structural inspector to please verify the change out 10/4/2002 8:53:48 AM
|
BLD-Framing/Rough-in | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PART |
Russ Owen
|
|
|
ceiling grid jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Conference | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | DONE |
Troy Cobbley
|
|
|
spoke with the contractor about location of the new duct smoke detectors. 9/24/2002 9:32:54 AM
|
BLD-Framing/Rough-in | 9/18/2002 | 9/18/2002 | 9/18/2002 | P | PART |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Framing/Rough-in | 9/4/2002 | 9/5/2002 | 9/5/2002 | A | PART |
Carl Dependahl
|
|
|
###-####; braces added at 24" oc, vertical member & redundant ceiling frame ok to delete. eng's letter to follow 9/5/2002 12:15:50 PM
|
BLD-Framing/Rough-in | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | FAIL |
Russ Owen
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. entry framing not per plan. 9/4/2002 10:42:16 AM
|
BLD-Framing/Rough-in | 8/22/2002 | 8/22/2002 | 8/22/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/22/2002 at 07:23:58. Contact: . framing ok. 8/23/2002 8:53:46 AM
|
BLD-Framing/Rough-in | 8/14/2002 | 8/14/2002 | 8/14/2002 | A | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 08/14/2002 at 07:23:55. Contact: ###-####. recall. 8/14/2002 4:52:37 PM
|
BLD-Framing/Rough-in | 8/14/2002 | 8/14/2002 | 8/14/2002 | P | PART |
Russ Owen
|
|
|
JIM ###-#### floor only recall, needs bracing and insulaton 8/14/2002 1:44:05 PM
|