BLD-Final | 5/27/2003 | 5/28/2003 | 5/28/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/27/2003 at 2:27:43 PM. Contact: ###-####.final ok sign offs in the archive. 5/28/2003 10:20:46 AM
|
Permanent Occupancy | | 5/28/2003 | 5/28/2003 | | DONE |
|
|
|
|
Code Occupancy Approval | 5/27/2003 | 5/27/2003 | 5/27/2003 | P | PASS |
Wm. Michael Meloy
|
|
|
Inspection noted compliance met. 5/27/2003 3:09:58 PM
|
FIRE-Final Inspection | 5/20/2003 | 5/20/2003 | 5/20/2003 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 5/20/2003 at 7:17:24 AM. Contact: ###-####.
|
FIRE-Final Inspection | 5/19/2003 | 5/19/2003 | 5/19/2003 | P | FAIL |
Rick Jackson
|
|
|
alarms and fire sprinklers okay; smoke vents won't open
|
BLD-Conference | 5/14/2003 | 5/14/2003 | 5/14/2003 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/14/2003 at 8:49:54 AM. Contact: ###-####. returns on exterior hand rails to be reduced at gaurdrail for spacing for chatch point. 5/14/2003 5:30:26 PM
|
BLD-Other | 4/3/2003 | 4/3/2003 | 4/3/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/3/2003 at 7:35:54 AM. Contact: ###-####.
|
BLD-Conference | 3/11/2003 | 3/11/2003 | 3/11/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/11/2003 at 10:49:51 AM. Contact: ###-####. conf ok stair review of handraillings. 3/11/2003 4:44:31 PM
|
BLD-Other | 2/11/2003 | 2/11/2003 | 2/11/2003 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/11/2003 at 8:43:40 AM. Contact: ###-####.c/n made ok 2/11/2003 3:47:41 PM
|
BLD-Framing/Rough-in | 1/31/2003 | 1/31/2003 | 1/31/2003 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/31/2003 at 10:35:30. Contact: ###-####. need special insp reports no requist to insp. roof sub-deck prior to roof covering all under special insp./ missing bolt at colum to gurder atchment. framinf of office ok for cover. 2/3/2003 8:40:44 AM
|
BLD-Concrete | 11/7/2002 | 11/8/2002 | 11/8/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/07/2002 at 10:27:02. Contact: ###-####. pending spec insp 11/8/2002 2:15:30 PM 11/8/2002 2:16:16 PM
|
BLD-Concrete | 10/22/2002 | 10/23/2002 | 10/23/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/22/2002 at 12:56:45. Contact: ###-####.first set of wall pannels rebar apears ok pending special insp report. 10/23/2002 3:36:00 PM
|
BLD-Concrete | 10/10/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Jim Storey
|
|
|
slab on grade. 10/11/2002 8:49:42 AM
|
BLD-Concrete | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/10/2002 at 10:42:54. Contact: ###-####.out of time 10/10/2002 7:43:36 PM
|