BLD-Final | 2/12/2003 | 2/13/2003 | 2/13/2003 | A | PASS |
Jim Storey
|
|
|
l/c isued. 2/13/2003 10:44:19 AM
|
BLD-Final | 2/12/2003 | 2/12/2003 | 2/12/2003 | P | PART |
Jim Storey
|
|
|
###-#### ###-####out of time 2/12/2003 5:56:25 PM
|
BLD-Footing | 9/9/2002 | 9/12/2002 | 9/12/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/09/2002 at 12:37:25. Contact: ###-####.
|
BLD-Footing | 9/9/2002 | 9/11/2002 | 9/11/2002 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 09/09/2002 at 12:36:35. Contact: ###-####. Cancelled by contractor 9/11/2002 11:55:37 AM
|
BLD-Footing | 9/9/2002 | 9/10/2002 | 9/10/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/09/2002 at 12:35:49. Contact: ###-####.rebar ok special insp. approved report pend. 9/10/2002 3:27:25 PM
|
BLD-Footing | 9/5/2002 | 9/6/2002 | 9/6/2002 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/05/2002 at 12:32:14. Contact: ###-####.walls ok sp report pending. 9/6/2002 10:41:35 AM
|
BLD-Footing | 9/3/2002 | 9/5/2002 | 9/5/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 10:16:33. Contact: ###-####.placed with special insp. 9/5/2002 3:55:16 PM
|
BLD-Footing | 9/3/2002 | 9/5/2002 | 9/5/2002 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 10:18:38. Contact: ###-####. pwsi 9/5/2002 4:00:44 PM
|
BLD-Footing | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 10:15:43. Contact: ###-####.placed with special insp. 9/4/2002 8:27:10 AM
|
BLD-Footing | 8/30/2002 | 9/3/2002 | 9/3/2002 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/30/2002 at 10:46:20. Contact: ###-####.special insp. mti epoxi and vert spacing ok. 9/3/2002 10:00:07 AM
|