BLD-Final | 12/23/2002 | 12/23/2002 | 12/23/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/23/2002 at 06:56:21. Contact: ###-####.
ok for perm. c of o 12/23/2002 11:14:24 AM
|
Permanent Occupancy | | 12/23/2002 | 12/23/2002 | | DONE |
|
|
|
|
BLD-Final | 12/17/2002 | 12/17/2002 | 12/17/2002 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/17/2002 at 08:23:58. Contact: ###-####.c/n posted 12/17/2002 10:27:22 PM
|
BLD-Final | 12/8/2002 | 12/9/2002 | 12/9/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/08/2002 at 17:34:28. Contact: ###-####.temp occ ok 12/10/2002 1:27:06 PM
|
FIRE-Final Inspection | 12/8/2002 | 12/9/2002 | 12/9/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/08/2002 at 17:33:52. Contact: ###-####.
|
FIRE-Final Inspection | 12/5/2002 | 12/6/2002 | 12/6/2002 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/05/2002 at 16:13:45. Contact: ###-####.
|
FIRE-Final Inspection | 12/5/2002 | 12/5/2002 | 12/5/2002 | A | FAIL |
Rick Jackson
|
|
|
need to test duct detectors and have smoke detector above panel reinstalled - the panel and duct detectors are all exsisting; need pull station repaired (open and the panel not in alarm); need resubmittals for sprinkler plans - not installed per plans
|
BLD-Wall cover | 11/20/2002 | 11/22/2002 | 11/22/2002 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/20/2002 at 15:47:37. Contact: ###-####....need sprinklers ok'd for entire t/i, has shell only ok at this point, according to 409 ...recommend no further tile or lids until resolved. C/N issued. 11/22/02 12:20:18 PM
|
BLD-Framing/Rough-in | 11/20/2002 | 11/20/2002 | 11/20/2002 | P | PART |
Dave Hannah
|
|
|
###-#### cieling grid ok to drop panels in rooms 110and 120 11/20/2002 3:37:16 PM
|
BLD-Framing/Rough-in | 11/4/2002 | 11/4/2002 | 11/4/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/04/2002 at 06:47:05. Contact: ###-####.walls ok to cover 11/4/2002 11:53:11 AM
|
BLD-Framing/Rough-in | 11/1/2002 | 11/1/2002 | 11/1/2002 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/01/2002 at 06:32:31. Contact: ###-####.ok to cover pending elec., and architect re-sub. on guage of walls , bracing and firewall? change 11/1/2002 2:11:06 PM
|