BLD-Final | 12/2/2002 | 12/3/2002 | 12/3/2002 | A | PASS |
Jim Storey
|
|
|
terry--lock box code is 193 for front door; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Energy code compliance | 10/15/2002 | 10/15/2002 | 10/15/2002 | P | PASS |
Steven Webb
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung 10/10/2002 1:28:50 PM all c/n items completed ok to insulate 10/10/2002 1:29:17 PM
|
BLD-Framing/Rough-in | 10/7/2002 | 10/8/2002 | 10/8/2002 | A | FAIL |
Dave Hannah
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie c/n on site do not insulate 10/8/2002 10:35:34 AM
|
BLD-Conference | 9/19/2002 | 9/19/2002 | 9/19/2002 | P | PART |
Steven Webb
|
|
|
SHEER ; Phone #: ###-#### Internet Inspection Request from: Annette Moore SHEAR NOT CONFERENCE--ok to side--gysum shear needed at rear of garage. 9/19/2002 2:50:35 PM
|
BLD-Foundation | 9/5/2002 | 9/6/2002 | 9/6/2002 | A | PART |
Alan Hauser
|
|
|
completing rebar 9/6/2002 2:16:19 PM
|
BLD-Foundation | 9/6/2002 | 9/6/2002 | 9/6/2002 | P | PART |
Steven Webb
|
|
|
may have been done this morning ###-####
|
BLD-Footing | 9/5/2002 | 9/5/2002 | 9/5/2002 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 09/05/2002 at 09:39:38. Contact: ###-####. 45% ready--no rebar at time of inspection. 9/5/2002 2:53:01 PM
|