BLD-Final | 3/31/2003 | 4/1/2003 | 4/1/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/31/2003 at 11:37:30 AM. needs hand rail to bouns room 4/1/2003 10:58:01 AM
|
BLD-Final | 4/1/2003 | 4/1/2003 | 4/1/2003 | P | PASS |
Dave Hannah
|
|
|
c.c # 23807 issued 4/1/2003 4:14:58 PM
|
BLD-Wall cover | 1/13/2003 | 1/14/2003 | 1/14/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/13/2003 at 10:52:10. Contact: .insulation ok all framing c/n items completed ok to cover 1/14/2003 9:26:02 AM
|
BLD-Framing/Rough-in | 1/9/2003 | 1/9/2003 | 1/9/2003 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/09/2003 at 08:14:25. Contact: . c/n on site ok to insulate 1/9/2003 2:04:53 PM
|
BLD-Framing/Rough-in | 1/6/2003 | 1/6/2003 | 1/6/2003 | P | NR |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 01/06/2003 at 09:08:17. Contact: . Need mechanical permit/inspection; informed contractor. 1/6/2003 4:35:08 PM
|
BLD-Other | 12/18/2002 | 12/19/2002 | 12/19/2002 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/18/2002 at 15:35:15. Contact: .I reveiwed letter from engineer checked all corrections ok to cover ext wall 12/19/2002 10:35:13 AM
|
BLD-Other | 12/11/2002 | 12/12/2002 | 12/12/2002 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/11/2002 at 14:54:02. Contact: .shear ok to cover areas without hold downs need engineer to review hold downs should have in stall rim joist type also need hold downs on garage front per new eng and back wall needs mst60s and mst 8s or 10s 12/12/2002 3:47:46 PM
|
BLD-Foundation | 10/8/2002 | 10/9/2002 | 10/9/2002 | P | PART |
Steven Webb
|
|
|
###-#### wip--rebar in place--85% ready. 10/9/2002 3:36:55 PM
|
BLD-Footing | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/08/2002 at 10:09:33. Contact: ###-####. wip ok 10/8/2002 2:09:53 PM
|