BLD-Final | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/03/2002 at 16:00:04. Contact: . per plan 12/4/2002 2:16:59 PM
|
BLD-Final | 12/4/2002 | 12/4/2002 | 12/4/2002 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 9/25/2002 | 9/25/2002 | 9/25/2002 | P | PART |
Carl Dependahl
|
|
|
need to verify complete blow-in & exterior envelope...gable ends/dormer walls at attic
|
BLD-Framing/Rough-in | 9/24/2002 | 9/25/2002 | 9/25/2002 | A | PASS |
Carl Dependahl
|
|
|
###-####, beam added, ladder frame ok, ok to cover 9/25/2002 3:23:44 PM
|
BLD-Energy code compliance | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | FAIL |
Carl Dependahl
|
|
|
LARRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs; adjust insul for r30 & r 38 as req'd, ok to cover attic area only. 9/24/2002 11:55:49 AM
|
BLD-Framing/Rough-in | 9/23/2002 | 9/24/2002 | 9/24/2002 | A | FAIL |
Carl Dependahl
|
|
|
LARRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs; need calcs for joist/beam carrying ldder frame, complete fireblocks, complete thru studs for attic trusses at 2nd floor...recall. 9/24/2002 11:55:00 AM
|
BLD-Energy code compliance | 9/19/2002 | 9/23/2002 | 9/23/2002 | P | NR |
Russ Owen
|
|
|
###-#### john . not ready called contractor and told him to recall.as still insulating no inspection done. 9/23/2002 3:11:55 PM
|
BLD-Framing/Rough-in | 9/19/2002 | 9/19/2002 | 9/19/2002 | P | FAIL |
Tom Arcoraci
|
|
|
LARRY ; Phone #: ###-#### Internet Inspection Request from: Annette Moore CN POSTED 9/19/2002 2:21:08 PM
|