Permit Information
Permit NumberBLD02-02200
StatusFinaled
Name US DEPARTMENT OF TRANSPORTATION
Site Address 3200 N LAKEHARBOR LN 161
Project NameWATERFRONT OFFICES
Customer Number 
ePlanReviewNo
Description
(U.S. DEPT. OF TRANSPORTATION)(WATERFRONT OFFICES-BLDG B-1ST FLR) New 1,801 sq.ft. office tenant on first floor of existing building per approved plans on file. Work to include new one-hour rated tenant demising wall, new one-hour rated corridor wall and ceiling at office entrance, new 20 minute rated door, new 45 minute rated wire glass sidelight, new interior walls and doors, interior finish, suspended ceiling work, mechanical work, plumbing work, and electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered for area increase. (PC#0597-02) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/7/20035/8/20035/8/2003APASS
DetailsTony Young
jack; Phone #: ###-#### Internet Inspection Request from: Darla Downs
ok for perm. occ. 5/8/2003 10:01:05 AM
Permanent Occupancy 5/8/20035/8/2003 DONE
Details
FIRE-Final Inspection4/30/20034/30/20034/30/2003APASS
DetailsTroy Cobbley
Fire alarm system finaled. OK for perm occupancy
BLD-Conference4/22/20034/23/20034/23/2003APART
DetailsTony Young
430 is checking 4/23/2003 9:38:41 AM
BLD-Conference4/22/20034/23/20034/23/2003ADONE
DetailsTroy Cobbley
I spoke with Charlie at simplexgrinnell and he said that they would get the inspection called in as soon as possible 4/25/2003 10:46:40 AM
BLD-Aging Inspection4/22/20034/22/20034/22/2003 PASS
DetailsTony Young
temp. occ. now,, waiting for trades 4/23/2003 9:39:34 AM
BLD-Final11/22/200211/22/200211/22/2002PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 11/22/2002 at 10:08:05. Contact: ###-####...need certify 45 min glazing at corr, verify htg NA? 11/22/02 5:53:14 PM
FIRE-Final Inspection11/22/200211/22/200211/22/2002PPART
DetailsTroy Cobbley
a temp. occupancy was given with dave millers permission until the fire alarm drawings have been approved, devices installed and tested 11/22/2002 3:47:04 PM
BLD-Final11/7/200211/8/200211/8/2002PCANC
DetailsTony Young
Scheduled by a contractor via Hello! on 11/07/2002 at 09:19:08. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/08/2002 at 08:13:56.
FIRE-Final Inspection11/7/200211/7/200211/7/2002PFAIL
DetailsTroy Cobbley
provide one 2-A10BC fire extinguisher with current inspection tag mounted with handle at 48" in a normal path of travel. See note #3, repair exit signs in path of eress from tenant space to building exterior then test exit signs. Provide City of Boise approved fire alarm plans. See note #2. Replace the insulation above the sprinkler uprights along the north half of the new demising wall. Provide ceiling tile at the sprinkler pendants and replace the missing canopies. Remove the dry wall splatter from the sprinkler pendants. Provide a suite address for tenant and provide a key for the "knox box" 11/7/2002 1:53:58 PM
BLD-Framing/Rough-in10/15/200210/16/200210/16/2002APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 10/15/2002 at 14:17:38. Contact: ###-####.
BLD-Framing/Rough-in10/9/200210/9/200210/9/2002PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 10/09/2002 at 09:16:36. Contact: ###-####.c/n posted on demising wall 10/9/2002 3:06:36 PM