Permit Information
Permit NumberBLD02-02477
StatusFinaled
Name CAFFERTY CONSTRUCTION
Site Address 121 N AL FRESCO PL
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 4843 sq. ft. two story single family dwelling with a 1082 sq. ft. finished basement, a 936 sq. ft. attached three car garage, a 200 sq. ft. 2nd level deck and stone patios per approved plans, all engineering/red-lining and attached requirement lists. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and 30 ft. defensible area will be maintained. Unless otherwise approved by the Boise City Fire Department, this structure shall be fitted with a 13D modified sprinkler system including all closets, bathrooms and barrier protection between garage and dwelling according to their listing requirements. The sprinkler flow alarm shall be attached to the residence smoke detection system. (1st floor 3078 sq. ft.)(2nd floor 1765 sq. ft.) PC #622 CFH #99-35 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/26/20043/26/20043/26/2004PPASS
DetailsTom Arcoraci
shawn; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Grading Inspection3/26/20043/26/20043/26/2004 PASS
DetailsRita DeYoung
Final grading and drainage complete and approved
FIRE-Final Inspection3/16/20043/17/20043/17/2004APASS
DetailsRick Jackson
Extend Permit 180 days 12/12/200312/12/2003 DONE
BLD-Energy code compliance5/15/20035/15/20035/15/2003PPASS
DetailsDave Hannah
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in5/15/20035/15/20035/15/2003PPASS
DetailsDave Hannah
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
FIRE-Sprinkler Rough-in5/15/20035/15/20035/15/2003PPART
DetailsRick Jackson
john tinting; Phone #: ###-#### Internet Inspection Request from: Barbara Moore tenting completed; okay to cover 5/15/2003 1:23:25 PM
BLD-Framing/Rough-in5/8/20035/9/20035/9/2003PFAIL
DetailsDave Hannah
john; Phone #: ###-#### Internet Inspection Request from: Annette Moore c/n on site ok to insulate 5/12/2003 8:39:46 AM
BLD-Framing/Rough-in3/13/20033/14/20033/14/2003APART
DetailsDave Hannah
shen shear wall; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to cover ext still needs to add 10 floor to floor straps they will add this on the in side can be checked at frame also gettig engineering on a hdq8 hold down 3/14/2003 11:23:01 AM
BLD-Framing/Rough-in3/5/20033/5/20033/5/2003PPART
DetailsDave Hannah
masonry fire places about 50% complete
BLD-Foundation12/30/200212/30/200212/30/2002PPART
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung work in progress forms and rebar ok still need to set holddowns 12/30/2002 1:48:45 PM
BLD-Footing12/20/200212/23/200212/23/2002APART
DetailsDave Hannah
steve; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie work in progress 75% complete 12/23/2002 9:58:17 AM
BLD-Footing12/20/200212/23/200212/23/2002ACANC
DetailsDave Hannah
BLD-Footing12/20/200212/20/200212/20/2002PCANC
DetailsDave Hannah
steve; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Foundation11/27/200212/2/200212/2/2002APART
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Amy Lawson basement walls ok to pour rebar and forms ok still need to set hold downs 12/2/2002 9:27:26 AM
BLD-Footing11/22/200211/25/200211/25/2002APART
DetailsTony Young
###-#### dave
basment ftgs ok, wip on grade 11/25/2002 12:39:02 PM
BLD-Grading Inspection11/25/200211/25/200211/25/2002 PASS
DetailsRita DeYoung
Footing subgrade for basement level has been approved by the geotechnical engineer