Permit Information
Permit NumberBLD02-02717
StatusFinaled
Name PENTALON CONSTRUCTION, INC.
Site Address 8561 W FAIRVIEW
Project NameASPEN SPRINGS APARTMENTS
Customer Number 
ePlanReviewNo
Description
Building 12 Type C Section 2) * A two hour area separation wall will be constructed to divide this building into two separate buildings. * To construct a new 12,270 sq.ft. two story with a basement, 12 unit apartment building. The basement is approximately 4,228 sq.ft. and the first and second floor are approximately 4,021 sq.ft each. All construction is per the approved plans and attached comment list. Work to include on site landscaping and parking lot. Refer to BLD 02-01071 for other side of area separation wall. MJP DRH02-00005 CUP01-00164 PC#284-02
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/20/20041/20/20041/20/2004PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 1/20/2004 at 11:17:54 AM. Contact: ###-####. OK for Perm Occ. :) 1/20/2004 3:49:10 PM
Permanent Occupancy 1/20/20041/20/2004 DONE
Details
FIRE-Final Inspection12/22/200312/23/200312/23/2003APASS
DetailsTroy Cobbley
fire alarm and fire life safety finaled 12/23/2003 11:01:36 AM
FIRE-Final Inspection12/22/200312/22/200312/22/2003PCANC
DetailsTroy Cobbley
rescheduled for tomorrow 12/22/2003 3:11:02 PM
Code Occupancy Approval  12/22/2003 PASS
LANDSCAPE IN PLACE FINAL SIGNED OFF.
BLD-Other10/10/200310/10/200310/10/2003APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/10/2003 at 7:22:06 AM. Contact: ###-####. Gypcrete at tubs. 10/10/2003 12:15:59 PM
BLD-Energy code compliance10/6/200310/6/200310/6/2003PPASS
DetailsJim Sly
###-#### chris Frame Pass 10/6/2003 5:17:34 PM
BLD-Framing/Rough-in10/1/200310/2/200310/2/2003AFAIL
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/1/2003 at 8:42:54 AM. Contact: ###-####. Firestopping and draftstop. 10/2/2003 10:22:58 AM
BLD-Framing/Rough-in10/1/200310/1/200310/1/2003PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/1/2003 at 8:30:20 AM. Contact: ###-####.
BLD-Framing/Rough-in8/27/20038/27/20038/27/2003PPART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 8/27/2003 at 9:11:16 AM. Contact: ###-####.
BLD-Framing/Rough-in8/25/20038/26/20038/26/2003APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 8/25/2003 at 11:52:09 AM. Contact: ###-####.c/n shear. 8/26/2003 1:54:09 PM
BLD-Aging Inspection3/21/20033/21/20033/21/2003 CANC
DetailsRuss Owen
work in progress. 3/27/2003 3:17:41 PM