Permanent Occupancy | | 12/2/2003 | 12/2/2003 | | DONE |
|
|
|
|
BLD-Final | 12/1/2003 | 12/1/2003 | 12/1/2003 | | DONE |
|
|
|
final ok for perm. occ./Jim
|
FIRE-Final Inspection | 11/26/2003 | 11/26/2003 | 11/26/2003 | P | PASS |
Troy Cobbley
|
|
|
fire life safety and fire alarm finaled
|
BLD-Final | 10/16/2003 | 10/16/2003 | 10/16/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/16/2003 at 9:26:13 AM. Contact: ###-####. Structural OK Pending Fire final Occ. OK for Temp Occ. 10/16/2003 1:37:10 PM
|
BLD-Final | 10/13/2003 | 10/13/2003 | 10/13/2003 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/13/2003 at 9:31:32 AM. Contact: ###-####.
|
FIRE-Final Inspection | 10/10/2003 | 10/10/2003 | 10/10/2003 | P | PART |
Troy Cobbley
|
|
|
Temp occupancy given until the NAC panel for the fire alarm system can be replaced
|
FIRE-Final Inspection | 10/8/2003 | 10/8/2003 | 10/8/2003 | P | FAIL |
Troy Cobbley
|
|
|
Life safety is ok but need to final fire alarm 10/8/2003 3:35:01 PM
|
FIRE-Final Inspection | 10/6/2003 | 10/6/2003 | 10/6/2003 | P | FAIL |
Troy Cobbley
|
|
|
no fire extinguishers installed, door hinges not adjusted, smoke detectors not tested 10/6/2003 3:28:32 PM
|
Code Occupancy Approval | | | 10/3/2003 | | PASS |
|
|
|
Compliance met.
|
BLD-Other | 8/7/2003 | 8/8/2003 | 8/8/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/7/2003 at 3:55:31 PM. Contact: ###-####.gyp crete areas of tubs etc. 8/12/2003 10:21:07 AMScheduled by a contractor via Hello! on 8/7/2003 at 3:55:31 PM. Contact: ###-####.gyp crete areas of tubs etc. 8/12/2003 10:21:21 AM
|
BLD-Framing/Rough-in | 8/4/2003 | 8/4/2003 | 8/4/2003 | P | FAIL |
Russ Owen
|
|
|
need gyp crete at some locations. 8/6/2003 12:52:14 PM
|
BLD-Energy code compliance | 7/28/2003 | 7/29/2003 | 7/29/2003 | P | PASS |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 7/24/2003 | 7/24/2003 | 7/24/2003 | P | PART |
Russ Owen
|
|
|
VINCENT ###-#### a 7/25/2003 9:22:34 AM Ok to insulate. 7/25/2003 9:23:49 AM
|
BLD-Framing/Rough-in | 7/22/2003 | 7/23/2003 | 7/23/2003 | P | FAIL |
Russ Owen
|
|
|
items addressed with contractor, Ok to insulate. 7/23/2003 5:15:14 PM
|
BLD-Conference | 7/18/2003 | 7/17/2003 | 7/17/2003 | P | PART |
Russ Owen
|
|
|
shear ok. 7/18/2003 12:19:44 PM
|
BLD-Framing/Rough-in | 7/16/2003 | 7/16/2003 | 7/16/2003 | P | PART |
Russ Owen
|
|
|
nails at corners. 7/18/2003 12:17:57 PM
|
BLD-Framing/Rough-in | 7/14/2003 | 7/15/2003 | 7/15/2003 | P | FAIL |
Russ Owen
|
|
|
###-#### vincent
|
BLD-Framing/Rough-in | 7/14/2003 | 7/14/2003 | 7/14/2003 | P | FAIL |
Russ Owen
|
|
|
###-#### . ext more nailing. 7/15/2003 9:07:01 AM
|
BLD-Framing/Rough-in | 7/11/2003 | 7/11/2003 | 7/11/2003 | P | PART |
Russ Owen
|
|
|
###-#### vincent (Interior ok, exterior needs nailing. 7/14/2003 3:56:08 PM
|
BLD-Foundation | 2/7/2003 | 2/10/2003 | 2/10/2003 | A | PASS |
Russ Owen
|
|
|
WALL; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Footing | 1/31/2003 | 2/3/2003 | 2/3/2003 | A | PASS |
Russ Owen
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|