BLD-Final | 3/11/2003 | 3/12/2003 | 3/12/2003 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/11/2003 at 4:01:13 PM. Contact: ###-####.c.c #23796 issued 3/12/2003 2:30:34 PM
|
BLD-Energy code compliance | 1/20/2003 | 1/21/2003 | 1/21/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/20/2003 at 17:17:22. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/20/2003 | 1/21/2003 | 1/21/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/20/2003 at 17:15:34. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/16/2003 | 1/17/2003 | 1/17/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/16/2003 at 12:02:24. Contact: ###-####.c/n on site ok to insulate 1/17/2003 11:35:55 AM
|
BLD-Framing/Rough-in | 1/14/2003 | 1/15/2003 | 1/15/2003 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/14/2003 at 12:38:45. Contact: ###-####. no seal package installed no inspection done at this time 1/15/2003 9:50:26 AM
|
BLD-Framing/Rough-in | 1/2/2003 | 1/3/2003 | 1/3/2003 | A | PART |
Dave Hannah
|
|
|
###-#### shear ok to cover ext 1/3/2003 9:15:46 AM
|
BLD-Foundation | 12/16/2002 | 12/16/2002 | 12/16/2002 | P | PART |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 12/16/2002 at 07:16:20. Contact: ###-####. WIP--5% ready at time of inspection. 12/16/2002 2:58:06 PM 12/16/2002 2:58:34 PM
|
BLD-Footing | 12/13/2002 | 12/13/2002 | 12/13/2002 | P | PART |
Dave Hannah
|
|
|
DANE; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie work in progress 20% complete checked setbacks all are tight 12/13/2002 3:51:40 PM
|