BLD-Final | 1/15/2004 | 1/16/2004 | 1/16/2004 | P | PASS |
Russ Owen
|
|
|
###-####- herb fn -re-insp Ok issued letter of compliance. 1/16/2004 2:42:43 PM
|
BLD-Final | 12/9/2003 | 12/9/2003 | 12/9/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/9/2003 at 11:07:15 AM. Contact: ###-####. Ok for temp pending schell core and mec for a perm. 12/10/2003 9:22:41 AM
|
FIRE-Final Inspection | 12/9/2003 | 12/9/2003 | 12/9/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety, fire sprinkler and fire alarm are finaled 12/9/2003 3:20:45 PM
|
Code Occupancy Approval | | | 12/9/2003 | | PASS |
|
|
|
LANDSCAPE IN AS REQUIRED FINAL OK
|
BLD-Energy code compliance | 12/4/2003 | 12/4/2003 | 12/4/2003 | P | PASS |
Russ Owen
|
|
|
ok new energy report. 12/5/2003 1:01:54 PM
|
BLD-Energy code compliance | 12/3/2003 | 12/3/2003 | 12/3/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/3/2003 at 10:14:46 AM. Contact: ###-####. I have recieved a new com check report with insulation values to match construction . 12/4/2003 1:52:37 PM
|
FIRE-Conference | 11/24/2003 | 11/25/2003 | 11/25/2003 | A | DONE |
Troy Cobbley
|
|
|
I spoke with the general contractor about curbing painting and the placement of a sign showing the location of the fire dept. connection 11/25/2003 1:28:55 PM
|
BLD-Energy code compliance | 11/13/2003 | 11/14/2003 | 11/14/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/13/2003 at 3:56:02 PM. Contact: ###-####. this schell and core showed R-30 ceiling , but has foam of R-18 also 2x4 walls shown on plans with R-19 on com check , architect re-ran report but the west space can not have R-19 value in a 2x4 wall will only get R-15 need to bump up another area or calc some of ceilng at penthoses to R-30 contractor on site will address and recall. 11/13/2003 11:53:16 PM Also 3 rear doors added which architect has ok"d. but need details for landings.11/13/2003 11:53:47 PM 11/13/2003 11:55:05 PM
|
BLD-Energy code compliance | 11/6/2003 | 11/7/2003 | 11/7/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/6/2003 at 3:59:20 PM. Contact: ###-####. recieved new mec check roof ok and walls insulated to r-11 ok. 11/7/2003 9:21:34 AM
|
BLD-Energy code compliance | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/3/2003 at 8:46:49 AM. Contact: ###-####.Posted c/n , insulation cn. 11/2/2003 10:03:39 PM
|
BLD-Framing/Rough-in | 10/30/2003 | 10/30/2003 | 10/30/2003 | P | PASS |
Russ Owen
|
|
|
Herb; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Framing/Rough-in | 10/13/2003 | 10/14/2003 | 10/14/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/13/2003 at 1:50:24 PM. Contact: ###-####. roof ok 10/13/2003 10:21:48 PM
|
BLD-Framing/Rough-in | 10/9/2003 | 10/13/2003 | 10/13/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/9/2003 at 4:17:47 PM. Contact: ###-####. needs nailing blocking at roof deck, marked on roof. 10/12/2003 10:37:32 PM
|
BLD-Other | 9/24/2003 | 9/25/2003 | 9/25/2003 | A | PART |
Russ Owen
|
|
|
went by job to check status special inspection is required for the cmu and is being provided. 9/28/2003 4:37:54 PM
|
FIRE-Supply Line Cover | 8/19/2003 | 8/19/2003 | 8/19/2003 | P | FAIL |
Troy Cobbley
|
|
|
BRUCE; Phone #: ###-#### Underground supply piping for the overhead sprinkler system has been installed in an open trench. There are no FIR permits for this project. I contacted bill alexander and left a correction notice that no work was to be continued and that the pipe is not to be covered or it will need to be dug back up. I spoke to Bruce and John with Commercial Fire and they stated that they were not aware that a permit was required for the underground work. 8/19/2003 1:34:35 PM
|
BLD-Footing | 8/13/2003 | 8/14/2003 | 8/14/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/13/2003 at 4:07:17 PM. Contact: ###-####.interior footings. 8/14/2003 12:36:10 PM
|
BLD-Foundation | 8/7/2003 | 8/7/2003 | 8/7/2003 | P | PART |
Russ Owen
|
|
|
south wall ok. 8/7/2003 12:28:39 PM
|
BLD-Footing | 8/6/2003 | 8/6/2003 | 8/6/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/6/2003 at 8:29:30 AM. Contact: ###-####.last pour of footing. 8/6/2003 3:19:09 PM
|
BLD-Footing | 8/4/2003 | 8/5/2003 | 8/5/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/4/2003 at 1:11:39 PM. Contact: ###-####. 8/5/2003 12:01:45 PM
|
BLD-Foundation | 8/1/2003 | 8/5/2003 | 8/5/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/1/2003 at 9:34:06 AM. Contact: ###-####.south area. 8/5/2003 12:01:17 PM
|
BLD-Footing | 8/4/2003 | 8/4/2003 | 8/4/2003 | A | PART |
Russ Owen
|
|
|
ok walls. 8/4/2003 3:12:05 PM
|
BLD-Footing | 8/1/2003 | 8/4/2003 | 8/4/2003 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 8/1/2003 at 9:33:21 AM. Contact: ###-####....unable to contact. 8/4/2003 5:09:45 PM
|
BLD-Footing | 7/29/2003 | 7/30/2003 | 7/30/2003 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/29/2003 at 3:50:21 PM. Contact: ###-####. north and east side ok 7/30/2003 10:57:21 AM
|