Information based on query as of Thursday, September 26, 2024.
Permit Information
Permit NumberBLD03-00878
StatusFinaled
Name RIVERSTONE BLDG CO
Site Address 810 N PIERCE ST Unit: 1
Project NameFoothills East Lot 1 Block 7
Customer Number 
ePlanReviewNo
Description
To construct a two story duplex per approved plans, all engineering/red-lining and attached requirement lists. Unit #1 (810 North Pierce Street) 1450 sq. ft. with a 551 sq. ft. attached two car garage and wood deck (lower level 525 sq. ft.)(main level 925 sq. ft.) Unit #2 (1305 East Shenandoah Drive) 1670 sq. ft. with a 495 sq. ft. attached two car garage and concrete patio (main level 950 sq. ft.) (upper level 720 sq. ft.) Note: This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and 30 ft. defensible space will be maintained. PC #257 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference10/28/200410/28/200410/28/2004ACANC
DetailsGary Ziegler
BLD-Final12/22/200312/23/200312/23/2003APASS
DetailsDave Hannah
Please call Jason at ###-#### to meet with inspector at site. Terry Records has signed off on grading-a bond was posted with Kathy. ; Phone #: ###-#### Internet Inspection Request from: Gary Gettman
BLD-Grading Inspection12/22/200312/22/200312/22/2003 BND
DetailsRita DeYoung
Rough grading is complete. Fine grading and revegetation are incomplete. Also, drainage system was modified without approval. Engineer has recommended a $700.00 bond to ensure that drainage will be revised to comply with the approved plan. The grading and drainage is conditionally approved upon receipt of a $700.00 bond.
BLD-Final12/19/200312/19/200312/19/2003PFAIL
DetailsDave Hannah
Please do as early as possible in the pm. Please call gary at ###-#### to meet inspector at project. Thanks; Phone #: ###-#### Internet Inspection Request from: Gary Gettman needs to finish deck and get terrys records sign off 12/19/2003 2:32:33 PM
BLD-Final12/18/200312/18/200312/18/2003PFAIL
DetailsDave Hannah
Gary; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes c/n items not complete c/n not on site 12/18/2003 2:33:27 PM
BLD-Final12/16/200312/16/200312/16/2003PFAIL
DetailsSteven Webb
Mech insp. also scheduled for this afternoon. Please come as late as possible. Call me to meet you at the site-Thanks. Gary; Phone #: ###-#### Internet Inspection Request from: Gary Gettman Correction notice issued--C/N located on kitchen counter in upper unit. 12/16/2003 3:30:33 PM
BLD-Energy code compliance10/30/200310/30/200310/30/2003PPASS
DetailsDave Hannah
gary--for duplex both units; Phone #: ###-#### Internet Inspection Request from: Marsha Smylieok to cover 10/30/2003 3:10:38 PM
BLD-Final10/28/200310/28/200310/28/2003PNR
DetailsDave Hannah
BLD-Framing/Rough-in10/27/200310/28/200310/28/2003PPASS
DetailsDave Hannah
Alicia; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok to insulate 10/28/2003 5:53:37 AM
BLD-Framing/Rough-in10/24/200310/24/200310/24/2003PCANC
DetailsDave Hannah
Jason; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Foundation8/1/20038/1/20038/1/2003PPART
DetailsDave Hannah
donny; Phone #: ###-#### Internet Inspection Request from: Barbara Moore work in progress 80% completed 8/1/2003 2:41:03 PM
BLD-Footing7/24/20037/25/20037/25/2003APASS
DetailsDave Hannah
donny; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Grading Inspection7/18/20037/18/20037/18/2003 PASS
DetailsRita DeYoung
Geotech approved footing subgrade