BLD-Final | 10/16/2003 | 10/17/2003 | 10/17/2003 | A | PASS |
Tom Arcoraci
|
|
|
Matt; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
|
BLD-Final | 10/16/2003 | 10/16/2003 | 10/16/2003 | P | FAIL |
Russ Owen
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/n posted. 10/16/2003 4:42:03 PM
|
BLD-Energy code compliance | 8/13/2003 | 8/14/2003 | 8/14/2003 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/13/2003 at 9:24:02 AM. Contact: ###-####.
|
BLD-Energy code compliance | 8/11/2003 | 8/11/2003 | 8/11/2003 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/11/2003 at 7:52:28 AM.
|
BLD-Framing/Rough-in | 8/11/2003 | 8/11/2003 | 8/11/2003 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/11/2003 at 7:51:52 AM.
|
BLD-Framing/Rough-in | 8/6/2003 | 8/6/2003 | 8/6/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/6/2003 at 8:14:37 AM. Contact: ###-####. Posted a c/n to put back prior c/n also complete insulation prior to a frame inspection. 8/6/2003 1:59:25 PM
|
BLD-Energy code compliance | 7/30/2003 | 8/1/2003 | 8/1/2003 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 7/30/2003 at 8:41:48 AM. Contact: ###-####. Left c/n to complete shear c/n and foam seal prior to calling for a frame inspection, called framer. 8/1/2003 4:11:09 PM
|
BLD-Framing/Rough-in | 7/30/2003 | 7/31/2003 | 7/31/2003 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 7/30/2003 at 8:40:09 AM. Contact: ###-####.Went over requirements with framer and posted c/n. 7/31/2003 6:38:45 PM
|
BLD-Foundation | 5/27/2003 | 5/27/2003 | 5/27/2003 | P | PART |
Jim Sly
|
|
|
###-#### chris Early start Found 5/27/2003 2:25:13 PM
|
BLD-Footing | 5/22/2003 | 5/22/2003 | 5/22/2003 | P | PART |
Russ Owen
|
|
|
###-#### chrisearly statrt appears ok. 5/22/2003 2:19:45 PM
|