Permanent Occupancy | | 8/19/2004 | 8/19/2004 | | DONE |
|
|
|
|
BLD-Conference | 7/14/2004 | 7/14/2004 | 7/14/2004 | P | PART |
Jim Sly
|
|
|
per your request for a reminder per y our request for a reminder 7/14/2004 5:28:37 PM see previous notes 7/14/2004 5:29:29 PM
|
BLD-Final | 3/16/2004 | 3/16/2004 | 3/16/2004 | P | DONE |
Jim Sly
|
|
|
MIKE; Phone #: ###-#### Internet Inspection Request from: Darla Downs 3/16/2004 1:57:08 PM OK for Temp Occ. only.......When bonding for landscape completed and Parcel issues resolved with P/Z. 3/16/2004 3:11:45 PM 3/16/2004 3:12:18 PM
|
BLD-Final | 3/12/2004 | 3/15/2004 | 3/15/2004 | A | PART |
Jim Sly
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs C/N....... Need signature for Temp from Code Enforc...or Verify bonding for unfinished landscaping. Install mirrors in baths.... Min 40" above floor, Need to verify Planning and Zoning OK with 2 Bldgs on one Parcel...... Provide conditions or agreements with P&Z for this issued prior to approval for Perm Occ. Obtain Perm Occ status within 90 days of this notice. OK for Temp. Occ. 3/15/2004 9:05:46 AM 3/15/2004 9:07:24 AM
|
FIRE-Final Inspection | 3/11/2004 | 3/12/2004 | 3/12/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 3/12/2004 11:33:47 AM
|
FIRE-Final Inspection | 3/11/2004 | 3/11/2004 | 3/11/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide approved door hardware on all of the interior doors. 3/11/2004 2:25:09 PM
|
BLD-Final | 3/9/2004 | 3/9/2004 | 3/9/2004 | P | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 3/9/2004 at 6:56:56 AM. Contact: ###-####. Needs all applicable signatutres on card prior to final. 3/9/2004 12:09:53 AM
|
BLD-Other | 3/3/2004 | 3/3/2004 | 3/3/2004 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/3/2004 at 6:57:32 AM. Contact: ###-####.
|
BLD-Energy code compliance | 1/15/2004 | 1/15/2004 | 1/15/2004 | P | PASS |
Russ Owen
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Conference | 1/14/2004 | 1/14/2004 | 1/14/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/14/2004 at 10:28:05 AM. Contact: ###-####. Frame Pass. 1/14/2004 2:03:49 PM
|
BLD-Framing/Rough-in | 1/12/2004 | 1/13/2004 | 1/13/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/12/2004 at 7:03:35 PM. Contact: ###-####. Need appr plans. 1/13/2004 10:11:49 AM
|
BLD-Framing/Rough-in | 1/13/2004 | 1/13/2004 | 1/13/2004 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 1/13/2004 at 10:15:59 AM. Contact: ###-####. no approved plans etc. posted c/n. 1/13/2004 2:50:23 PM
|
BLD-Foundation | 11/6/2003 | 11/6/2003 | 11/6/2003 | P | PART |
Steven Webb
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Perimeter foundation walls ok, no inspection done or was ready on columns. 11/6/2003 1:55:55 PM 11/6/2003 1:56:18 PM
|
BLD-Footing | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PASS |
Jim Sly
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs Off ustick....N. side ....going W. turn B 4 pink house. 11/3/2003 2:16:20 PM
|