BLD-Concrete | 3/12/2004 | 3/15/2004 | 3/15/2004 | A | PASS |
Troy James
|
|
|
MIKE; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 3/11/2004 | 3/12/2004 | 3/12/2004 | A | PART |
Troy James
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs
wip 3/12/2004 9:45:09 AM
|
BLD-Conference | 11/10/2003 | 11/10/2003 | 11/10/2003 | P | CANC |
Steven Webb
|
|
|
|
BLD-Conference | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | DONE |
Dave Hannah
|
|
|
talked with concrete crew about cold weather concreret 11/5/2003 12:50:23 PM
|
BLD-Footing | 10/30/2003 | 10/31/2003 | 10/31/2003 | A | PART |
Russ Owen
|
|
|
I got a call yester day from the engineers rep, he went out to site he said the are now making the footings continous and about half done, I now am back out at 9:30 am they did not call this in for an inspection but , I wanted to make shure footing was contionous at all locations this pour is now and they are cleaning out the araes that sluff in at this time. pump truck has now pulled up. 10/30/2003 5:15:42 PM
|
BLD-Footing | 10/29/2003 | 10/30/2003 | 10/30/2003 | A | FAIL |
Russ Owen
|
|
|
Jimmy; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes. Engineer to inspect c/n posted , also notified contractor and engineers office. 10/30/2003 11:41:18 AM
|
BLD-Footing | 10/30/2003 | 10/30/2003 | 10/30/2003 | A | CANC |
Russ Owen
|
|
|
wrong date. 10/30/2003 5:09:24 PM
|
BLD-Grading Inspection | 10/23/2003 | 10/23/2003 | 10/23/2003 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade approved by the geotechnical engineer.
|