Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD04-00094
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 112 E BANNOCK ST
Project NameST LUKES-MRI & BD ADDTN
Customer Number 
ePlanReviewNo
Description
ST. LUKE'S MRI and BD SHELL & CORE ADDITION - To construct a 790 square foot, three story stair enclosure and a 1505 square foot MRI Vault at the basement. This is a shell and core addition being constructed on the south side of the existing St. Luke's Hospital building along with selective demolition at each floor. As well as a 330 square foot, one story, shell and core entry addition at the south end of the west wing. To remove all vehicular traffic on Bannock St. between 1st St and Ave A and turn area into a park. This is a shell and core permit only. Tenant improvement permits will be required to finish these additions for occupancy. Plan Modification - The scope of work for this permit has been modified to delete the proposed 790 sq. ft. stair enclosure and 1505 sq. ft. MRI Vault at the basement portion of this project. The scope of work has been further modified to enlarge the entry addition at the south end of the west wing to include a 375 square foot, shell and core area at the first floor above a 350 square foot ground level space. This new portion of this addition is structurally designed for a future second and third floor addition above. All construction per the approved plans and attached comment list. PC#033-04/DRH03-00212/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/10/20062/10/20062/16/2006 PASS
DetailsDave Hannah
DOC - Permit Finaled2/16/20062/16/20062/16/2006PPASS
DetailsDave Hannah
BLD-Aging Inspection11/21/200511/21/200511/21/2005 NR
DetailsTom Arcoraci
BLD-Final6/14/20056/16/20056/16/2005ANR
DetailsDave Hannah
phill; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa needs other trades to sign off
FIRE-Final Inspection6/14/20056/16/20056/16/2005APART
DetailsForrest France
Life safety issues passed inspection, final pending sign off on sprinkler permit fir05-00160 (flow switch test).
FIRE-Final Inspection6/16/20056/16/20056/16/2005PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final3/21/20053/22/20053/22/2005ANR
DetailsDave Hannah
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 3/22/2005 10:03:12 AM area for 1st floor west wing ok 3/22/2005 10:12:48 AM
FIRE-Final Inspection3/21/20053/21/20053/21/2005PFAIL
DetailsTroy Cobbley
dan; Phone #: ###-#### Need fire sprinkler permit for the modified underground that is being installed. Bill Alexander and I spoke to Phil and Stan with St. Lukes construction about this issue. 3/21/2005 4:24:15 PM
FIRE-Conference3/18/20053/18/20053/18/2005ADONE
DetailsBill Alexander
Troy Cobbley and Bill Alexander did inspection on underground work and find extensive fire service supply main work being installed in "tunnel" and "Fire Sprinkler Control Room". Treasure Valley Fire Protection doing work without a permit. System is off so no stop work order was issued. Red Tagged the underground and requested permit approval per IFC 2003 Section 105.1.1, 105.7 and 901.3 and Boise Municipal Code 7-01-08 Section 105.1.4.
BLD-Conference3/7/20053/7/20053/7/2005PDONE
DetailsDave Hannah
Need to walk the bannock project thanks phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble
BLD-Footing8/23/20048/23/20048/23/2004PDONE
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/23/2004 at 9:48:30 AM. Contact: ###-####. using spec insp 8/24/2004 10:27:17 AM
BLD-Aging Inspection8/2/20048/2/20048/2/2004 PASS
DetailsDave Hannah