BLD-Final | 4/4/2006 | 4/5/2006 | 4/5/2006 | P | PASS |
Tony Young
|
|
|
Mark (office ###-####) -- call 1st before insp for access code; prefer after 2PM (need 30 minutes notice); prefer David Hannah (who last inspected and is familiar with the situation); Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
DOC - Permit Finaled | 4/5/2006 | 4/5/2006 | 4/5/2006 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 4/3/2006 | 4/4/2006 | 4/4/2006 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/3/2006 at 9:06:51 PM. Contact: ###-####. no acess no answer on phone
|
BLD-Final | 4/2/2006 | 4/3/2006 | 4/3/2006 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/2/2006 at 6:58:56 PM. Contact: ###-####. needhandrails and beef up gaurd railing on ext
|
BLD-Grading Inspection | 3/24/2006 | 3/24/2006 | 3/24/2006 | | DONE |
|
|
|
Rough grading is complete however fine grading and restoration of the disturbed hillside must still be done. Also, the drainage swale at the front of the lot must be restored to the original grades. To ensure completion of the incomplete work a $500.00 bond is required. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Wall cover | 8/3/2005 | 8/3/2005 | 8/3/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/3/2005 at 6:30:49 AM. Contact: ###-####. drywall shear ok
|
BLD-Energy code compliance | 7/26/2005 | 7/27/2005 | 7/27/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/26/2005 at 5:33:44 PM. may have interior shear to see
|
BLD-Framing/Rough-in | 7/27/2005 | 7/27/2005 | 7/27/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/27/2005 at 7:13:19 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/26/2005 | 7/26/2005 | 7/26/2005 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/26/2005 at 7:56:08 AM. Contact: ###-####. re-scheduled for am,, out of time
|
BLD-Framing/Rough-in | 7/19/2005 | 7/19/2005 | 7/19/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/19/2005 at 7:23:57 AM. Contact: ###-####. need to seal draftstop, holes in plates,, etc,,, ok to insulate
|
BLD-Framing/Rough-in | 7/18/2005 | 7/18/2005 | 7/19/2005 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/18/2005 at 8:01:09 AM. Contact: ###-####. was after 5pm,, asked to call back in
|
BLD-Framing/Rough-in | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/15/2005 at 7:54:06 AM. Contact: ###-####. needs seal pack 1st
|
BLD-Other | 4/12/2005 | 4/12/2005 | 4/12/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/12/2005 at 5:52:54 AM. Contact: ###-####.
ext shear ok 4/12/2005 4:30:41 PM
|
BLD-Foundation | 7/9/2004 | 7/9/2004 | 7/9/2004 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/9/2004 at 7:26:25 AM. Contact: ###-####.
wip on basement walls 7/9/2004 3:48:36 PM
|
BLD-Footing | 6/1/2004 | 6/1/2004 | 6/1/2004 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/1/2004 at 7:20:12 AM. Contact: (208) Mark ###-####, please call first for access. thanks.
ok to pour when ready 6/1/2004 4:54:11 PM
|
BLD-Footing | 5/24/2004 | 5/24/2004 | 5/24/2004 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/24/2004 at 7:20:11 AM. Contact: ###-####. Mark -- please call first for access thanks.
c/n posted 5/24/2004 11:05:49 AM
|
BLD-Grading Inspection | 5/5/2004 | 5/5/2004 | 5/5/2004 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade approved by the geotechnical engineer
|