BLD-Foundation | 11/3/2006 | 11/6/2006 | 11/7/2006 | A | PART |
Tony Young
|
|
|
jeff overton ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie landscape ftgs/walls
|
BLD-Final | 5/8/2006 | 5/9/2006 | 5/9/2006 | P | PART |
Tony Young
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung conf only,, need hand rails, stair nosings, etc
|
BLD-Grading Inspection | 4/27/2006 | 4/27/2006 | 4/27/2006 | | DONE |
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 1/12/2006 | 1/13/2006 | 1/13/2006 | A | PASS |
Tony Young
|
|
|
wall cover -- jeff ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 1/12/2006 | 1/13/2006 | 1/13/2006 | A | PASS |
Tony Young
|
|
|
wall cover -- jeff ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Wall cover | 1/11/2006 | 1/11/2006 | 1/11/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/11/2006 at 7:40:41 AM. Contact: ###-####. ceiling ok to cover on front part on home
|
BLD-Wall cover | 1/4/2006 | 1/5/2006 | 1/5/2006 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/4/2006 at 5:06:42 PM. Contact: ###-####. ok to cover garage lid
|
BLD-Conference | 12/12/2005 | 12/12/2005 | 12/12/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/12/2005 at 7:41:49 AM. Contact: ###-####. recieved "letter of ok" on shear from engineer,, ok to insulate garage pending electrical rough in,,, then call prior to sheetrock for garage only
|
BLD-Framing/Rough-in | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | NR |
Tony Young
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Barbara Moore need letter from structural engineer stating ok as built on bracing/ shear panels due to being covered,,, need trades 1st before real frame inspection,,,
|
BLD-Framing/Rough-in | 8/11/2005 | 8/12/2005 | 8/12/2005 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/11/2005 at 7:41:39 PM. Contact: ###-####.
|
BLD-Concrete | 4/1/2005 | 4/1/2005 | 4/1/2005 | P | PART |
Troy James
|
|
|
call 1st before insp jeff-- ###-#### cell
concrete deck for driveway and garage floor rebar ok 4/1/2005 3:19:34 PM
|
BLD-Foundation | 11/18/2004 | 11/18/2004 | 11/18/2004 | P | PASS |
Troy James
|
|
|
Jeff-Upper driveway retaining wall-Jeff will not be there-; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
|
BLD-Footing | 11/10/2004 | 11/10/2004 | 11/10/2004 | P | PART |
Troy James
|
|
|
Jeff; Phone #: ###-#### Internet Inspection Request from: Jan Rice
retaining wall at road 11/12/2004 7:59:47 AM
|
BLD-Grading Inspection | 11/10/2004 | 11/10/2004 | 11/10/2004 | | DONE |
|
|
|
Footing subgrade for upper retaining wall and bridge pier have been approved by the geotechnical engineer.
|
BLD-Foundation | 10/20/2004 | 10/21/2004 | 10/21/2004 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 10/20/2004 at 8:34:14 AM.
|
BLD-Foundation | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 10/4/2004 at 7:17:27 AM.
|
BLD-Footing | 9/27/2004 | 9/28/2004 | 9/28/2004 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 9/27/2004 at 8:53:11 AM. Contact: ###-####.
|
BLD-Grading Inspection | 9/28/2004 | 9/28/2004 | 9/28/2004 | | DONE |
|
|
|
footing subgrade for the garage and basement have been approved by the geotech
|
BLD-Foundation | 8/30/2004 | 8/31/2004 | 8/31/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 11:53:58 AM. Contact: ###-####.
|
BLD-Footing | 8/9/2004 | 8/10/2004 | 8/10/2004 | A | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 8/9/2004 at 9:05:04 AM. Contact: ###-####.
|
BLD-Footing | 8/3/2004 | 8/5/2004 | 8/3/2004 | A | CANC |
Troy James
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Aimee Hughes
|
BLD-Grading Inspection | 8/3/2004 | 8/3/2004 | 8/3/2004 | | PASS |
|
|
|
geotechnical engineer has approved the footing subgrade for the "lower bench", (area below the kitchen and mudroom)
|
BLD-Foundation | 6/28/2004 | 6/28/2004 | 6/28/2004 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 6/28/2004 at 7:57:01 AM. Contact: ###-####. Foundation for mechanical room and kitchen dining room above. 6/28/2004 1:44:06 PM
|
BLD-Footing | 6/14/2004 | 6/14/2004 | 6/14/2004 | P | PART |
Troy James
|
|
|
jeff; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Ok to place concrete footing for dining, kitchen area. 6/14/2004 2:50:53 PM
|
BLD-Grading Inspection | 6/14/2004 | 6/14/2004 | 6/14/2004 | | PASS |
Rita DeYoung
|
|
|
Footing subgrade forkitchen,dining,living and mechanical rooms approved by the geotechnical engineer.
|
BLD-Foundation | 4/30/2004 | 4/30/2004 | 4/30/2004 | P | PART |
Tony Young
|
|
|
Jeff; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
mech. room walls,, wip 4/30/2004 3:29:45 PM
|
BLD-Footing | 4/15/2004 | 4/16/2004 | 4/16/2004 | A | PART |
Dave Hannah
|
|
|
JEFF; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok to pour ftgs for column pads and ftgs for master bedroom 4/16/2004 9:27:21 AM
|
BLD-Grading Inspection | 3/30/2004 | 3/30/2004 | 3/30/2004 | | PASS |
Rita DeYoung
|
|
|
footing subgrade approved by the geotechnical engineer.
|