BLD-Aging Inspection | 4/17/2006 | 4/17/2006 | 4/17/2006 | | CANC |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 4/17/2006 | 4/17/2006 | 4/17/2006 | A | PASS |
Mike Jordan
|
|
|
confirmed that ele. has finaled the shell and core.
|
BLD-Final | 11/16/2004 | 11/17/2004 | 11/17/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/16/2004 at 1:08:24 PM. Contact: ###-####.
still need final approval from elec. insp. for shell/core.
letter of compliance ok for this permit pending electrical insp. sign off.
Letters received from both the special inspection firm, and the engineer of record, confirming compliance with all design, material, and construction elements. 11/17/2004 1:43:24 PM
|
FIRE-Alarm Testing | 11/16/2004 | 11/17/2004 | 11/17/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety, fire alarm and fire sprinkler passed 11/17/2004 9:14:40 AM
|
BLD-Final | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/15/2004 at 12:11:49 PM. Contact: ###-####. Pat will reschedule 11/16/2004 8:52:03 AM
|
FIRE-Alarm Testing | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | FAIL |
Troy Cobbley
|
|
|
Duct detector shut down wired wrong and supervisory signal were not sent in 11/16/2004 10:08:43 AM
|
FIRE-Final Inspection | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | FAIL |
Troy Cobbley
|
|
|
Repair two emergency lights and final fire alarm 11/16/2004 10:07:51 AM
|
BLD-Final | 11/12/2004 | 11/15/2004 | 11/15/2004 | P | CANC |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/12/2004 at 1:56:23 PM. Contact: ###-####.
|
FIRE-Final Inspection | 11/12/2004 | 11/15/2004 | 11/15/2004 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 11/12/2004 at 1:55:43 PM. Contact: ###-####.
|
FIRE-Conference | 11/3/2004 | 11/3/2004 | 11/3/2004 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the fire alarm contractor about separate annunciation for the backflow preventor and placement of the horn. 11/3/2004 3:09:12 PM
|