BLD-Final | 8/17/2005 | 8/18/2005 | 8/18/2005 | A | PASS |
Mike Jordan
|
|
|
mark ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 8/18/2005 | 8/18/2005 | 8/18/2005 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | PASS |
Tony Young
|
|
|
mark ###-#### conf on signoffs
|
BLD-Grading Inspection | 8/8/2005 | 8/8/2005 | 8/8/2005 | | DONE |
|
|
|
Final grading and drainage approved
|
BLD-Energy code compliance | 3/24/2005 | 3/25/2005 | 3/25/2005 | P | PASS |
Tony Young
|
|
|
mark ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | PASS |
Tony Young
|
|
|
mark ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Conference | 3/21/2005 | 3/21/2005 | 3/21/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 3/21/2005 at 11:25:22 AM. Contact: ###-####.
walk through w/ Mark,,, need trades prior to insulation,,, need egress window sill height,,,44",,, need letter from eng. on all systems 3/21/2005 2:59:54 PM
|
BLD-Framing/Rough-in | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | NR |
Tony Young
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
need arch. approvals on changes 1/27/2005 11:47:35 AM
|
BLD-Concrete | 9/3/2004 | 9/7/2004 | 9/7/2004 | A | PART |
Tony Young
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
piers and pier walls 9/7/2004 11:13:07 AM
|
BLD-Footing | 8/26/2004 | 8/27/2004 | 8/27/2004 | A | PART |
Tony Young
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
cololm ftgs,,, stair ftgs 8/27/2004 11:56:37 AM
|
BLD-Foundation | 8/9/2004 | 8/10/2004 | 8/10/2004 | A | PART |
Tony Young
|
|
|
Tim;phone# ###-####
basement/retaining walls,,, rebar ok per plan,,, concrete is 4000 psi,,, pending special inspection report,,, no note in plan review, but confirmed w/ architect,, needed on walls only,,, contractor will get letter. 8/10/2004 1:55:45 PM
|
BLD-Concrete | 8/9/2004 | 8/9/2004 | 8/9/2004 | P | NR |
Tony Young
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Footing | 7/26/2004 | 7/27/2004 | 7/27/2004 | P | PART |
Tony Young
|
|
|
Tim -- he has mud coming at 3:00. thanks.; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
wip 7/27/2004 3:40:05 PM
|
BLD-Grading Inspection | 7/26/2004 | 7/26/2004 | 7/26/2004 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|