Permit Information
Permit NumberBLD04-02653
StatusFinaled
Name JAYO CONSTRUCTION
Site Address 3209 N NORTH MOUNTAIN LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 3408 sq. ft. two story single family dwelling with a 1036 sq. ft. finished daylight basement, a 806 sq. ft. attached three car garage, a 152 sq. ft. covered entry porch and a 683 sq. ft. covered wood deck above daylighted basement area per approved plans, all engineering/red-lining and attached condition list. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof system and 30 ft. defensible space shall be maintained. (1st floor 2167 sq. ft.)(2nd floor 1241 sq. ft.) PC #665 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/31/20066/1/20066/1/2006APASS
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: SHANE JAYO
DOC - Permit Finaled6/1/20066/1/20066/1/2006PPASS
DetailsTony Young
c of o issued
BLD-Grading Inspection4/27/20064/27/20064/27/2006 BOND
The rough grading and drainage have been completed at the above mentioned address. However, a retaining wall along the north side must be completed. For this the engineer has recommended a bond of $2,000.00. Upon receipt of this bond the grading and drainage is conditionally approved.

BLD-Final4/18/20064/19/20064/19/2006PNR
DetailsTony Young
Shane -- call 1st for access code; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
BLD-Other9/2/20059/2/20059/2/2005PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 9/2/2005 at 10:42:06 AM. Contact: ###-####.
int. ok after nailing edges and adding a stud
BLD-Framing/Rough-in8/24/20058/24/20058/24/2005PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 8/24/2005 at 11:23:58 AM. Contact: ###-####.
energy code ok also,,, will need int. shear
BLD-Framing/Rough-in8/19/20058/22/20058/22/2005AFAIL
DetailsTony Young
Tony call me and I will meet you out there.
c/n posted,, ok to insulate
BLD-Framing/Rough-in8/18/20058/19/20058/19/2005PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/18/2005 at 12:10:01 PM. Contact: ###-####. Shearwall insp. only. checked tie downs and strapping. framinginsp stil needed and t verify solid blocking at bearing points.
BLD-Framing/Rough-in8/18/20058/22/20058/18/2005PCANC
DetailsTony Young
Scheduled by a contractor via Hello! on 8/18/2005 at 12:01:03 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 18 2005 12:06PM.
BLD-Framing/Rough-in8/17/20058/17/20058/17/2005PCANC
DetailsTony Young
Scheduled by a contractor via Hello! on 8/17/2005 at 9:35:49 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 17 2005 9:38AM.
BLD-Foundation2/2/20052/2/20052/2/2005PPART
DetailsTony Young
Ed; Phone #: ###-#### Internet Inspection Request from: Jan Rice
wip 2/2/2005 3:14:12 PM
BLD-Footing1/28/20051/31/20051/31/2005APART
DetailsTony Young
shane; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
house and garage walls 1/31/2005 2:02:17 PM
BLD-Footing1/27/20051/28/20051/28/2005PNR
DetailsTony Young
shane; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Grading Inspection1/25/20051/25/20051/25/2005 DONE
Footing subgrade for the main level and garage foundation has been approved by the geotechnical engineer
BLD-Foundation1/12/20051/13/20051/13/2005APART
DetailsTroy James
ed; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip rebar in place ok 1/13/2005 11:04:29 AM
BLD-Footing1/7/20051/11/20051/11/2005APART
DetailsDave Hannah
For basement area only////ed ###-#### ok to pour ftgs for basement 1/11/2005 10:37:38 AM
BLD-Grading Inspection1/4/20051/4/20051/4/2005 DONE
Footing subgrade for basement and spread footing on the west edge of the patio approved by the geotechnical engineer. All loose, disturbed, saturated or frozen soil must be removed from trenches prior to pouring concrete.